December 15, 2017
Just a reminder that next week on Highway 7 between Edgeley Boulevard/Interchange Way and the Highway 400 bridge, crews will be installing 10 hydro poles and 3 stub poles. Please see below for further details.
what you need to know:
work dates*: Monday, Dec. 18 to Friday, Jan. 26
work hours*: 9am–3:30pm
*Please note: As with other road construction projects, some work may be rescheduled due to weather or other variables. We are committed to providing advance notice whenever possible. Check twitter.com/vivanext for last-minute updates.
be moved. This Sunday,December 17 is the opening of the Vaughan Metropolitan Centre [VMC] transit hub, which includes the opening for service of the TTC Line 1 Subway Extension. For more information, check out vivanext.com/VMCopening.
Michelle Goland
Community Liaison Specialist