Skip navigation

Project Updates» Highway 7 West \ Vaughan

project status

phase 1 under construction

expected completion
Dec. 2016 / 2019

30%
completed

view project timeline

subscribe to notices

Project Updates» Highway 7 West \ Vaughan

filter by month show all

January 23, 2015

Hwy 7 West, lane reductions east of Hillside Ave

January 23, 2015 In preparation for ongoing telecommunications relocation work, crews will be reducing lanes along Highway 7, just east and just west of Bowes Road for line painting. Please see below for details on temporary lane reductions: line painting on Highway 7, east of Hillside Avenue dates of work*: Friday, January 23 work hours: [...]
read more 13144

January 7, 2015

telecommunications work continues from Hillside Avenue to Baldwin Avenue

As work extends throughout the winter months, crews will continue the next segment of underground telecommunications relocation along Highway 7 West, from Hillside Avenue to just east of Baldwin Avenue. work dates*: Work begins on January 8, for approximately 12 weeks* work hours: 7am to 7pm work location: Crews will be working on the boulevards [...]
read more 12903

December 19, 2014

rapidway construction continues along highway 7 west over the winter

Construction is well underway for the first phase of vivaNext rapidways in the City of Vaughan, and the transformation can be seen along Highway 7 West. Although construction will continue throughout the winter months from Edgeley Boulevard to Bowes Road, here’s an update on the progress made in 2014: The road has been widened and [...]
read more 12797

November 12, 2014

important changes to traffic patterns and intersections

Our vivaNext Highway 7 project is well underway and we’re moving into the next phase of construction that includes building the rapidway, station platforms and canopies between Jane Street and the CN Bridge. To complete this work in the median, eastbound and westbound lanes are shifting to their final location. As a result, this requires [...]
read more 12154

November 7, 2014

paving continues between Jane Street and the CN Bridge

Crews will begin the next section of base-layer paving between Jane Street and the CN Bridge starting tomorrow. These paving activities will be completed in sections on both the north and south sides of Highway 7. Please see details below for traffic and pedestrian impacts. Please note that all of the following work activities are [...]
read more 11978

November 3, 2014

paving continues on highway 7 west

As crews continue road widening and installing new curbs along Highway 7 West, the next segment of base-layer paving will begin between Jane Street and the CN Bridge. These paving activities will be completed in sections over the next week and will include closures on both the north and south sides of the Creditstone Road/Highway [...]
read more 11895

September 30, 2014

paving begins on highway 7 west from jane to creditstone

As part of road widening, crews have completed underground utility relocations on the south side of Highway 7 from Jane Street to the CN Bridge. The next step is to begin base-layer paving. Paving activities will be completed in sections along Highway 7 over the next year and will include some road closures. Please see [...]
read more 11312

September 16, 2014

road widening & utility relocation continues, keele to bowes/baldwin

Over the summer, crews have been busy widening the road from Jane Street to the CN Bridge and relocating underground infrastructure, including sewer, hydro and telecommunications east of the CN Bridge to Bowes Road/Baldwin Avenue. As we continue road widening to complete as much road construction as possible prior to the winter months, we have planned road closures [...]
read more 11118

August 15, 2014

median removals on highway 7 [keele - bowes/baldwin]

In order to accommodate road widening and an upcoming traffic shift on Highway 7 West, medians will be removed and traffic lanes will be reduced from Keele Street to Bowes Road/Baldwin Avenue. Please see below for further details. Work dates*: Starting on August 19, for approximately 5 weeks* Work hours: Monday – Friday from 9:30am-3:30pm [...]
read more 10379

July 19, 2014

road widening begins along highway 7 west

The transformation is underway along Highway 7 West. Crews have been busy relocating underground infrastructure, including sewer, hydro and telecommunications, and starting next week road widening will begin from Jane Street to the CN Bridge. In order to accommodate multiple work activities related to this construction, traffic lanes will be shifted, reduced and narrowed. Please [...]
read more 9940
....