Skip navigation

Project Updates» Highway 7 West \ Vaughan

project status

phase 1 under construction

expected completion
Dec. 2016 / 2020

30%
completed

view project timeline

subscribe to notices

project updates» Highway 7 West \ Vaughan

filter by month show all

May 21, 2015

paving this weekend at Keele and Highway 7

May 21, 2015 It’s an exciting time as the transformation of Hwy. 7 has made significant progress. As crews continue platform work at the future vivastations, the next segments of base-layer paving will begin between Edgeley Blvd./Interchange Way to Keele St. These paving activities will be completed in sections over the next two months and [...]
read more 15384

May 20, 2015

temporary phone/internet outage at Creditstone and Highway 7

May 20, 2015 Bell and construction crews are working around the clock to repair a temporary outage that is impacting all Bell services, including phone and Internet, in the Creditstone and Highway 7 West area. what you need to know: Some service is expected to be restored later this afternoon, with the remainder gradually being [...]
read more 15334

May 19, 2015

Hwy 7 West is getting ready for greenery

May 19, 2015 It’s an exciting time as the transformation continues along Highway 7 West with significant progress. Concrete planters are being installed in the sidewalk areas of Highway 7 for future trees, shrubs and plants. See below for the detailed information. preparing for greenery on Highway 7 West dates of work*: starting the week [...]
read more 15314

May 13, 2015

Vaughan: temporary lane closures along Highway 7 West

May 12, 2015 Please see the information below about temporary lane closures along Highway 7 West, from Jane Street to Keele Street. line painting from Jane Street to the CN Bridge dates of work*: Tuesday, May 12* work hours: 7pm to 6am Crews are line painting along Highway 7 from Jane Street to the CN [...]
read more 15142

May 7, 2015

temporary lane closures from Bowes to Baldwin

May 07, 2015 Please see the information below about temporary lane closures along Highway 7 West, from Bowes Rd. to Baldwin Ave. line painting from Bowes Road/Baldwin Avenue dates of work*: Thursday, May 7* work hours: 8pm to 1am Crews will be painting road lines along Hwy 7 from Bowes Road/Baldwin Avenue to the GO [...]
read more 15006

April 27, 2015

Hwy 7 W – lane closures Edgeley to Jane, and at Bowes

April 24, 2015 As part of rapidway construction, storm sewer and hydro installations continue along the north side of Highway 7. Crews will be working at the intersection of Highway 7 West and Bowes Road for approximately three days, and between Edgeley Boulevard and Jane Street for approximately one week*. Please see the information below [...]
read more 14774

April 20, 2015

Vaughan: construction activity Hwy 400 – Bowes Rd

April 17, 2015 In the next several days crews will be at work on Highway 7 near Highway 400, Jane Street and Bowes Road. Please see the information below about temporary lane closures. line painting at Bowes Road dates of work*: Saturday, April 18 work hours: extended from 7am to noon description: From Bowes Road [...]
read more 14638

April 17, 2015

Vaughan: lane closures on Creditstone and Keele at Hwy 7

April 10, 2015 Crews will be working on traffic signal installation at Creditstone Road, and on storm sewer installation at Keele Street starting as early as Monday, April 13. Please see below for detailed information about temporary lane closures at each location. traffic signal installations at Creditstone Road dates and hours of work*: Monday, April [...]
read more 14549

March 31, 2015

Overnight work from Keele – Bowes/Baldwin starting April 1

March 31, 2015 Spring is upon us and crews are busy installing new underground storm sewer pipes and drains along the north side of Highway 7, east of Keele Street to Hillside Avenue. To complete this underground work prior to the start of road widening, planned overnight work and traffic shifts will be necessary. Please [...]
read more 14226

March 24, 2015

Vaughan: overnight lane closures for utility work

March 24, 2015 As part of rapidway construction, storm sewer upgrades will be underway in the overnight hours on Highway 7 starting March 25 for approximately two weeks. Please see the information below about temporary lane closures: storm sewer work – Edgeley Boulevard to Jane Street dates of work*: starting Wednesday, March 25 for approximately [...]
read more 14034
....