Skip navigation

Project Updates» Yonge Street \ Richmond Hill and Newmarket

project status

rapidway under construction

expected completion
Dec. 2018

18%
completed

view project timeline

subscribe to notices

project updates» Yonge Street \ Richmond Hill

filter by month show all

February 17, 2017

hydro wire installation continues across Yonge at High Tech and Spruce

February 17, 2017 On Sunday, crews will be installing overhead hydro service wires on Yonge Street at the High Tech Road and Spruce Avenue intersections. To accommodate this work, north and southbound traffic along Yonge will be stopped for a short duration as crews hoist wires up to the poles at each intersection. hydro work [...]
read more 34874

February 10, 2017

overnight closures at Clarissa, Yongehurst, May, and Harding

February 10, 2017 As water main crews work overnight next week along Yonge Street, there will be temporary overnight closures to Clarissa Drive, Yongehurst Road, May Avenue and Harding Boulevard E/W. Due to the nature of this work, at times, there will be construction-related noise, dust and vibration disturbances from equipment and trucks. Please read [...]
read more 34765

February 9, 2017

traffic signal work at Weldrick and May

February 9, 2017 Starting tomorrow, crews will be removing traffic poles, installing new traffic poles and hanging temporary traffic lights along Yonge at Weldrick Road W/E and May Avenue. work dates*: Feb. 10 for approximately two weeks work hours: 7am-7pm what you need to know: Crews will begin at Weldrick and then move to the [...]
read more 34724

February 9, 2017

hydro pole installation on Yonge Street, north of Gamble Road/19th Avenue

February 9, 2017 To prepare for the widening of Yonge Street, hydro crews will install new hydro poles set further back from the road on the east and west side of Yonge, just north of Gamble Road/19th Avenue. After the poles have been installed, existing power lines will be transferred to the new poles. work [...]
read more 34654

February 7, 2017

retaining wall construction at Yonge and 19th

February 7, 2017 As part of the transformation of Yonge Street in Richmond Hill, we will be building another retaining wall along Yonge. Starting tomorrow, crews will begin building a retaining wall and grading on the east side of Yonge between 19th Avenue and Devonsleigh Boulevard. Retaining walls are built to provide stability between two [...]
read more 34611

January 30, 2017

line painting between Weldrick Road and Harding Blvd

January, 30 2016 Tonight, crews will be painting new traffic lines on Yonge Street between Weldrick Road and Harding Boulevard. work dates*: Monday, Jan. 30 work hours: 9pm–2am, Overnight Crews will be working overnight tonight, Monday, Jan. 30 to remove and then re-paint traffic lines on Yonge from just south of Weldrick to just north [...]
read more 34476

January 27, 2017

duct bank installation across Yonge at Gamble/19th

January 27, 2017 Crews will be installing a duct bank [a structure which gathers together and encases utility cables] across Yonge Street just north of Gamble Road/19th Avenue. work dates*: Monday, Jan. 30 for approximately two weeks work hours: 7am-7pm stage 1 – approximately three days Crews will begin working on the west side of [...]
read more 34439

January 27, 2017

hydro wire installation across Yonge from Carrville to 407

January 27, 2017 On Sunday, crews will be installing overhead hydro service wires on Yonge, between Carrville Road/16th Avenue to the Highway 407 overpass. To accommodate this work, north and southbound traffic along Yonge will be intermittently stopped throughout work hours as crews hoist wires up to the poles. hydro work installation work dates*: Sunday, [...]
read more 34402

January 23, 2017

hydro work at Yonge & Nottingham

January 23, 2017 Crews will be installing overhead hydro service wires tomorrow at the intersection of Yonge Street and Nottingham Drive. hydro work installation work dates*: Tuesday, January 24, 2017 work hours: 9am–3:30pm Crews will be completing the installation of new power cables at the intersection of Yonge and Nottingham. This will involve a disruption [...]
read more 34169

January 13, 2017

gas main installation from Weldrick Rd. E to Harding Blvd. E

January 13, 2017 Gas crews are continuing to progress along Yonge Street in Richmond Hill. Gas main installation will begin on the east side of Yonge, from Weldrick Road East to just north of Harding Boulevard East. Read on for more details. what you need to know work dates*: Starting Monday, Jan. 16, for approximately [...]
read more 33979
....