Project Updates» Davis Drive \ Newmarket

project status

rapidway open

expected completion
Nov. 2015

93%
completed

view project timeline

subscribe to notices

project updates» Davis Drive \ Newmarket

filter by month show all

May 27, 2016

sidewalk planting begins on Davis Drive

May 27 2016 Rapidway median planting is now complete and crews are ready to begin planting trees, shrubs and perennials in the sidewalk planters along Davis Drive between Yonge Street and Patterson Street / Roxborough Road. Next week, crews will focus on the area between Yonge Street and Longford / Parkside Drive. Once complete, we [...]
read more 24023

May 20, 2016

final median planting on Davis Drive

May 20 2016 Next week, crews will continue planting trees, shrubs and perennials in the rapidway medians along Davis Drive between Keith Bridge and Patterson Street / Roxborough Road. This is the third and final phase of median planting. Once complete, crews will begin planting along the sidewalks on Davis. work dates*: Tuesday, May 24 [...]
read more 23658

May 13, 2016

trail access closure and sidewalk work on Davis Drive

May 13, 2016 Next week, crews will be working on pedestrian walkways along Davis. Please read on for details. access to Tom Taylor Trail closed west of Keith Bridge The pedestrian walkway that leads to the Tom Taylor Trail on the south side of Davis, west of Keith Bridge, will be closed as crews install [...]
read more 23336

May 12, 2016

tree planting continues on Davis Drive

May 12, 2016 Next week, crews will continue planting trees, shrubs and perennials in the rapidway medians along Davis Drive between Parkside Drive / Longford Drive and Main Street. This is the second phase of median planting. The third and final phase will be from Keith Bridge to Main Street. work dates*: Monday, May 16 [...]
read more 23281

May 6, 2016

trees are coming to Davis Drive!

May 6, 2016 Blue and yellow make green! Mix blue buses with Viva yellow and you get a green way of life. Next week, crews will begin planting trees, shrubs and perennials in the rapidway medians along Davis Drive. The work will take place over the next few weeks and will happen in three phases. [...]
read more 23013

May 3, 2016

#ThanksDavisDr! See you at the Community Cleanup & Fun Day

May 3, 2016 blue and yellow make green! Mix blue buses with Viva yellow and you get a green way of life. Join us on May 7 in showing some community spirit and enjoy the outdoors at the Town of Newmarket’s Community Cleanup & Fun Day. Location: Newmarket Recreation Youth Centre & Sk8 Park [RYC] [...]
read more 22897

April 29, 2016

construction update for Davis Drive

April 29, 2016 We’re in the final stretch of the transformation of Davis Drive! Over the next few months, there will be a lot of activity on the corridor as we work to complete the project. Next week, crews will be working in several areas along the corridor. Please read on for details. Davis and [...]
read more 22772

April 26, 2016

correction: sidewalk work in front of Southlake Regional Health Centre

April 26, 2016 Yesterday we issued a construction bulletin detailing sidewalk work at Southlake Regional Health Centre. In the bulletin, we incorrectly stated that the work would begin next week when in fact it is this week. We apologize for any confusion we may have caused. If you have questions about the rapidway project, please [...]
read more 22675

April 25, 2016

sidewalk work in front of Southlake Regional Health Centre

April 25, 2016 Tomorrow, crews will begin building the permanent sidewalk on the south side of Davis Drive from Southlake Regional Heath Centre’s Davis entrance to Roxborough Road. Planters will be put in place, followed by concrete pouring and interlocking paver stone installation. work dates*: Tuesday, April 26 to Friday, June 10 work hours*: 7am-7pm [...]
read more 22649

April 14, 2016

sidewalk work on Davis Drive

April 14, 2016 Over the next several months, crews will be completing sidewalks and planting trees and shrubs along with other work activities. Crews will begin removing temporary asphalt from two areas along Davis Drive, followed by pouring of new permanent concrete sidewalk and installing paver stones. Crews will be working on the south side [...]
read more 22391
....