Project Updates» Davis Drive \ Newmarket

project status

under construction

expected completion
Dec. 2015

70%
completed

view project timeline

subscribe to notices

project updates» Davis Drive \ Newmarket

filter by month show all

April 17, 2015

Davis construction activities Apr 18-24: expect night and weekend work

April 17, 2015 Please see below for information on Davis Drive construction taking place between Longford Drive and Barbara Road and around Keith Bridge, starting tomorrow and continuing through next week [Apr 18-24]. These construction activities include weekend and night work. weekend work Crews will be working on the south side of Davis Drive in [...]
read more 14615

April 16, 2015

Park and Ride expansion at Davis Drive and Highway 404

April 16, 2015 Construction is starting on a new park and ride lot at Davis Drive and Highway 404 that will make it easier for people to take public transit. The carpool lot, currently located at Davis Drive and Highway 404 and owned by the Ministry of Transportation, will be expanded to become a park [...]
read more 14503

April 10, 2015

Davis Drive road widening: Keith Bridge to Superior and Barbara to Longford

April 10, 2015 Over the next several weeks, road widening activities will begin in two locations along Davis Drive. Further details are provided below. Work date: As early as Monday, April 13, for several weeks Work hours: Monday – Friday 7:00am – 7:00pm. At times weekend and night work may be required* Please note: there [...]
read more 14390

April 2, 2015

Davis construction activities — Keith Bridge to Prospect start April 6

April 2, 2015 Over the next several months, there will be multiple work activities on the south side of Davis Drive, between Keith Bridge to just east of Prospect Street. Crews will be installing sanitary and storm sewers and widening the road. Following this work, curbs will be installed and the area will be paved. [...]
read more 14249

March 27, 2015

Davis Drive construction activities: March 30 – April 2

March 27, 2015 Please see below for information on Davis Drive construction activities taking place in several locations along the corridor next week [March 30 – April 2]. electrical work from Keith Bridge to Charles Street Crews will be performing electrical work along the south side of Davis Drive between the Tannery and just east [...]
read more 14083

March 20, 2015

Davis Drive, work near Main and Huron Heights-Alexander

March 20, 2015 Please see below for information on Davis Drive spring cleaning as well as construction activities taking place around Main Street and Huron Heights Drive/Alexander Road next week [March 23-27]. completion of telecommunications ductbank Despite the cold weather we have had over the past few months, our telecommunications crew has made great progress [...]
read more 13872

March 9, 2015

Davis Drive construction activities: March 10-13

March 9, 2015 Please see below for information on Davis Drive line painting and work taking place around Main Street and the Tannery entrance this week. line painting along Davis Crews will be line painting traffic lines, stop bars and crosswalks at intersections and side streets in various locations along Davis from Yonge Street to [...]
read more 13647

March 5, 2015

change to accessing Bolton Avenue from Davis Drive – Friday, March 6

March 5, 2015 As construction of the vivastation in front of Southlake Hospital continues to make great progress, the access lane to Bolton Avenue from Davis Drive will be temporarily closed tomorrow as crews pour concrete to form the westbound platform. Work date: Friday, March 6* Work hours: From approximately 7:00am-1:00pm What you need to [...]
read more 13612

March 3, 2015

gas main installation on Parkside Drive

March 3, 2015 Gas crews will be installing a new gas main on the re-aligned portion of Parkside Drive starting in early March. This is the final gas segment to be installed on the corridor. Work dates: Starting Thursday, March 5, for approximately 3 weeks Work hours: Monday – Friday, 7am to 6pm. At times [...]
read more 13580

February 27, 2015

Davis Drive construction activities Feb 28-March 5

February 27, 2015 Please see below for an update on Davis Drive construction activities taking place over the weekend and into next week [February 28 – March 5]. weekend work at 161 Davis Drive Work dates: Saturday, February 28 and Sunday, March 1 Work times: 7:00am – 5:00pm* What you need to know As crews [...]
read more 13545
....