Project Updates» Davis Drive \ Newmarket

project status

under construction

expected completion
dec. 2015

54%
completed

view project timeline

subscribe to notices

Project Updates» Davis Drive \ Newmarket

filter by month show all

September 19, 2014

important notice: main st. north closed at davis

In order to begin construction of the vivastations at Main Street and Davis Drive and complete as much road construction as possible prior to the winter months, planned closures of Main Street North will take place next week. To accommodate necessary storm sewer, watermain installation and road widening activities the closures will be in affect [...]
read more 11230

September 2, 2014

Tom Taylor Trail detour and retaining wall construction

Work Dates: starting this week until the beginning of November What you need to know: Crews will first build a decorative armour stone wall along the Seniors’ Meeting Place patio and the Tom Taylor Trail. During retaining wall construction, the Tom Taylor Trail will be temporarily detoured on the east side of the building through [...]
read more 10715

August 29, 2014

New way to access 446 Davis Drive

Please be advised that effective, August 29, 2014: Vehicles will only be able to make an eastbound right-turn from Davis into the 446 Davis Drive plaza  Left-turns into the plaza from Davis are no longer possible There will be one-way traffic flow around the north side of the building. Signs will be in place to [...]
read more 10665

August 22, 2014

paving on davis and night work: august 27-29

Road widening is progressing on Davis Drive and next week paving will continue in the newly widened areas. Paving locations and more details can be found below. Paving dates: Wed Aug 27 to Fri Aug 29* Times: 6:00am — 9:00pm* paving locations and details: Westbound lanes on Davis from Yonge Street to Barbara Road Northbound [...]
read more 10503

August 15, 2014

road widening activities on Davis, east of Bolton Ave.

Over the next several months, there will be multiple work activities on the north side of Davis Drive, just east of Bolton Avenue. Crews are installing watermain, storm sewer, widening the road and will later pave, in preparation for the construction of a vivastation at Southlake Regional Health Centre that will start later this year. [...]
read more 10403

August 14, 2014

paving on davis: July 28, 29 & 30

Crews will pave the base-layer of Davis Drive in sections next week. Please see below for paving locations and details. Eastbound lanes from the entrance of Southlake Regional Health Centre to Roxborough Road Westbound lanes from Vincent to just east of Hill Street Eastbound lanes from east of Niagara to just west of Main Street [...]
read more 10366

August 7, 2014

Main and Davis ongoing construction activities and night work

Beginning tonight and continuing for a month, crews will be completing several work activities at the intersection of Davis Drive and Main Street. Main Street is one of the future vivastation locations. Before construction of the vivastations can begin, crews first need to install sanitary sewers. They will then widen the south side of the [...]
read more 10253

July 28, 2014

yonge street construction work in newmarket

update: yonge street construction work in newmarket Having received comments from Mayor Van Bynen, Regional Councillor Taylor and the community regarding traffic flow throughout Newmarket, there will be no further daytime lane closures for the vivaNext project on Yonge Street in Newmarket until daytime lane closures associated with the Mulock Drive road resurfacing project are [...]
read more 10130

July 25, 2014

paving on davis: july 28, 29 & 30

Crews will pave the base-layer of Davis Drive in sections next week. Paving locations and more details can be found below. The final coat of asphalt will be paved next year prior to the rapidway opening. Paving dates: Monday, July 28 – Wednesday, July 30* Times: 6:00am — 9:00pm* Paving locations on davis: Click here [...]
read more 10107

June 27, 2014

construction of the first vivastation set to start on Davis

Construction of the east and westbound vivastation platforms at Parkside/Longford and Davis Drive will start in early July. This will be an important moment in starting to see the transformation of Davis become a reality! Below are more details on the construction of the first vivastation on Davis Drive. how to build a vivastation There [...]
read more 9704
....