Skip navigation

Project Updates» Davis Drive \ Newmarket

project status

under construction

expected completion
dec. 2015

70%
completed

view project timeline

subscribe to notices

Project Updates» Davis Drive \ Newmarket

filter by month show all

December 19, 2014

from messy to marvelous – davis drive year in review

As another year comes to a close, we wanted to provide you with an update on the Davis Drive rapidway project, including the progress made this year and a look ahead to upcoming winter work. check out the progress Construction of the east and westbound platforms for the Longford/Parkside vivastation is well underway. The steel [...]
read more 12826

December 5, 2014

paving along davis next week: dec 8-12

Crews will be paving next week in the areas below. Paving dates: Monday, December 8 to Friday, December 12* Hours of operation: from approximately 7:00am — 7:00pm Note: This work is weather-dependent and can be rescheduled at any time Paving areas: main street & davis drive intersection Impacts: There will be lane closures required throughout [...]
read more 12660

November 17, 2014

make way for the first vivastation on davis

If you’ve been travelling along Davis Drive lately, you’ll notice an exciting development taking shape at Longford/Parkside Drive: construction of the vivastations is progressing. Out of the 6 vivastation platforms to be built along Davis, the two platforms at Longford/Parkside are the furthest along. Construction of the westbound platforms at Main Street and Southlake Hospital [...]
read more 12223

November 11, 2014

updated paving along davis nov 24-28

Crews will finish paving in the areas listed below this week. Paving dates: Monday, November 24 to Friday, November 28* Hours of operation: from approximately 7:00am — 7:00pm Note: This work is weather-dependent and can be rescheduled at any time Paving areas: Southwest, northwest and southeast corners of the Yonge and Davis intersection Impact: During [...]
read more 12069

November 10, 2014

demolition at 299 davis drive

Starting this month, crews will be working at the vacant building located on the north side of Davis Drive, east of Hill Street [see map below]. Please be advised that there will be noise and dust associated with this work. what you need to know: Building removal and site clean-up will take approximately 1 month. [...]
read more 12017

October 29, 2014

road widening and storm work on davis drive

Over the next several weeks, there will be multiple work activities on the south side of Davis Drive from east of Parkside Drive/Longford Drive to east of Niagara Street. Crews will be installing storm sewer, widening the road, and will later install new curbs and pave the base-layer of asphalt. Please see below for further [...]
read more 11813

October 17, 2014

update: davis construction activities oct. 18-24

An update on Davis Drive construction activities is provided below and includes information on paving, night work and intermittent lane closures. paving continues along davis Paving dates: Began today and will continue on Saturday October 18 and Monday, October 20 Hours of operation: from approximately 7:00am – 7:00pm Note: Please expect traffic delays as intermittent [...]
read more 11685

October 15, 2014

update: davis night work rescheduled

The night work scheduled to take place this week along and around Davis Drive has been rescheduled due to the changing weather forecast. Please see below for the revised dates and work hours. paving The paving that was scheduled to take place overnight starting tonight [October 15-17] has been rescheduled to take place during the [...]
read more 11611

October 10, 2014

night work on davis starting oct. 14

Next week, crews will be working overnight in several locations along Davis in order to continue paving and complete necessary underground work in the center of the road. There will be noise associated with these night work operations. Please see more details below. paving along davis Paving dates: Wednesday, October 15 to Friday, October 17* [...]
read more 11549

October 9, 2014

tom taylor trail north of davis temporarily detoured

Starting as early as Tuesday, October 14, the Tom Taylor Trail , north of Davis Drive will be temporarily detoured for approximately two weeks. The trail detour will be between George Richardson Park [at the north] and the Seniors’ Meeting Place on Davis Dr. [at the south]. The detour route includes: Bayview Parkway, Heman Street, [...]
read more 11490
....