Project Updates» Davis Drive \ Newmarket

project status

under construction

expected completion
2015

47%
completed

view project timeline

subscribe to notices

Project Updates» Davis Drive \ Newmarket

filter by month show all

July 25, 2014

paving on davis: july 28, 29 & 30

Crews will pave the base-layer of Davis Drive in sections next week. Paving locations and more details can be found below. The final coat of asphalt will be paved next year prior to the rapidway opening. Paving dates: Monday, July 28 – Wednesday, July 30* Times: 6:00am — 9:00pm* Paving locations on davis: Click here [...]
read more 10107

June 27, 2014

construction of the first vivastation set to start on Davis

Construction of the east and westbound vivastation platforms at Parkside/Longford and Davis Drive will start in early July. This will be an important moment in starting to see the transformation of Davis become a reality! Below are more details on the construction of the first vivastation on Davis Drive. how to build a vivastation There [...]
read more 9704

June 26, 2014

paving on davis from hill st. to longford: june 27

Crews have widened the road on the north side of Davis Drive from Hill Street to Longford Drive and will now begin base-layer paving. Additional paving activities will be completed in other sections over the next year, prior to the rapidway opening at the end of 2015. Please see paving details for the Hill to [...]
read more 9662

May 9, 2014

lane reductions on Davis from Main to the Tannery

Over the next several months there will be multiple work activities on Davis Drive, just east of Main Street around the CN Rail tracks, the Tannery, Seniors’ Meeting Place and the Newmarket Chamber of Commerce. To accommodate these operations, traffic lanes will be shifted and reduced on Davis from Main Street to the Tannery Mall. [...]
read more 9014

March 28, 2014

construction on Prospect St. from Davis Dr. to Queen St.

Starting next week, crews will begin installing new underground telecommunications [ductbank] along the east side of Prospect Street. The work will start at Southlake Hospital’s parking garage entrance and move south, stopping at Queen Street. work dates: Starting the week of March 31 for approximately 3 weeks* overnight work hours: For the first 3 nights [...]
read more 8582

February 12, 2014

road closure: Lundy’s Lane closed at Davis Drive – February 20 – 28

As crews install ductbank [a structure that gathers together and encases telecommunications wires underground] across Lundy’s Lane [just north of Davis Drive], the road will be temporarily closed for about two weeks. This is one of a few necessary road closures on Lundy’s Lane to complete infrastructure and road work. Additional short-term road closures will be required [...]
read more 8138

January 31, 2014

overnight work and Longford Drive closure February 3–5

Please be advised that Longford Drive will be temporarily closed for two days as crews perform two nights of watermain work. Further details are provided below. Longford closed at Davis Drive from: Tuesday, February 4 – Wednesday, February 5* Note: This closure will stay in place overnight [24 hours]. Overnight watermain work: Monday, February 3 [...]
read more 7992

January 16, 2014

entrance closure: Southlake Regional Health Centre at Davis temporarily closed

As crews install ductbank [a structure that gathers together and encases telecommunications wires underground] across the Davis Drive entrance of Southlake Regional Health Centre, the entrance will be temporarily closed for about a week. Davis Drive entrance to Southlake closed from: Monday, January 20 – Friday, January 24* what you need to know [see map]: [...]
read more 7780
....