Project Updates» Highway 7 East \ Markham and Richmond Hill

project status

under construction

expected completion
Jan. 2014

95%
completed

view project timeline

subscribe to notices

project updates» Highway 7 East \ Markham and Richmond Hill

filter by month show all

March 28, 2015

Highway 7 curb lane closures, week of Mar. 30

March 27, 2015 Please see the information below about temporary lane closures along Highway 7 East from Monday, March 30 to Thursday, April 2 for work on the north and south sides of the road. landscape maintenance Dates/times: Monday, March 30 to Thursday, April 2, 9:30am – 3:30pm Locations: Highway 7 East, various locations from [...]
read more 14162

March 20, 2015

Hwy 7 East traffic signal work, week of Mar. 23

March 20, 2015 Please see the information below about overnight temporary lane closures from Monday, March 23 to Friday, March 27 for traffic signal work on Highway 7 East. traffic signal work on Highway 7 East Dates/times: 1am to 5am in the early mornings from Monday, March 23 to Friday, March 27 Locations: Highway 7 [...]
read more 13847

March 18, 2015

Line painting on Highway 7 East

March 18, 2015 Please see the information below about temporary traffic disruptions on Thursday, March 19 due to line painting in locations along Highway 7 East, from Highway 404 to Warden Avenue. Line painting on Highway 7 East Dates/times: Thursday, March 19, 10am – 3pm Locations: Eastbound traffic lanes of Highway 7, under the Highway [...]
read more 13820

January 5, 2015

now open! welcome to your new vivastation.

January 5, 2015 We are growing, right along with you, as we open another rapidway section located south of Highway 7 along South Town Centre Boulevard, Cedarland Drive and Warden Avenue. Riders can now board Viva at the new Cedarland Station, located on the south side of Cedarland at Warden. The rapidway travels along the [...]
read more 13076

December 22, 2014

Cedarland Drive now open in Markham

December 22, 2014 Please be aware that Cedarland Drive, located south of Highway 7 and west of Warden Avenue, is now open. Cedarland was previously closed for rapidway construction, and now has 2 additional rapidway lanes and a new Cedarland vivastation. When travelling on Cedarland and adjacent streets of South Town Centre Boulevard and Warden, [...]
read more 13099

December 19, 2014

rapidway opening soon south of highway 7

Crews have been busy completing work on the final stretch of rapidway down South Town Centre Boulevard, Cedarland Drive and out to Warden Avenue. As we approach the holiday season and the end of the year, please be aware of the activities you can expect to see: bus driver training Viva drivers began training on [...]
read more 12835

November 28, 2014

paving work, november 30-december 3

The following paving work is now rescheduled on Town Centre Boulevard and South Town Centre Boulevard. Please be advised that this work is weather dependent and there will be noise and potential traffic delays. Some sidewalks and crosswalks will be closed temporarily. Pedestrians please follow directional signs. town centre boulevard, intermittent closures Location: Town Centre [...]
read more 12520

November 27, 2014

paving work, November 30-December 2

The following paving work is now rescheduled on Town Centre Boulevard and South Town Centre Boulevard. Please be advised that this work is weather dependent, and there will be noise and potential traffic delays. Some sidewalks and crosswalks will be closed temporarily. Pedestrians please follow directional signs. town centre boulevard closure Location: Town Centre north [...]
read more 12472

November 21, 2014

paving work, November 25-27

The following paving work is scheduled on Town Centre Boulevard and South Town Centre Boulevard. Please be advised that this work is weather dependent, and there will be noise and potential traffic delays. Some sidewalks and crosswalks will be closed temporarily. Pedestrians please follow directional signs. town centre boulevard closure Location: Town Centre Blvd. north of [...]
read more 12374

November 6, 2014

paving work, starting november 7

The following paving work is scheduled to start on Friday, November 7 on South Town Centre Boulevard. Please be advised that this work is weather dependent, and there will be noise and potential traffic delays. Police officers will be directing traffic at intersections where work is underway. Some sidewalks and crosswalks will be closed temporarily. [...]
read more 11952
....