Project Updates» Highway 7 East \ Markham and Richmond Hill

project status

under construction

expected completion
dec. 2014

90%
completed

view project timeline

subscribe to notices

Project Updates» Highway 7 East \ Markham and Richmond Hill

filter by month show all

October 24, 2014

paving work on highway 7 east: oct. 25 – 28

The following paving work is scheduled to take place this week on Highway 7 East at the areas indicated below. Please be advised that this work is weather dependent, and there will be noise and traffic delays. Follow detour signs and give yourself enough time to get to your destination or plan alternate routes lunar [...]
read more 11726

October 10, 2014

paving work on highway 7 east: oct. 15–17

The following paving work is scheduled to take place this week on Highway 7 East at the areas indicated below. Please be advised that this work is weather dependent, and there will be noise and significant traffic delays. Please follow detour signs and give yourself enough time to get to your destination or plan alternate routes. [...]
read more 11571

October 3, 2014

paving work on highway 7 east, oct. 3 – 6

The following paving work is scheduled to take place this weekend on South Town Centre Boulevard and Montgomery Court at the areas indicated below. Please be advised that this work is weather dependent. Motorists and transit users should expect traffic delays. Please give yourself enough time to get to your destination or plan alternate routes. [...]
read more 11364

September 26, 2014

construction work on highway 7 east, sept. 29 – oct. 3

The following lane closures and construction work is scheduled to take place next week on Highway 7 at the intersections indicated below. There are some detours in effect, please look for signage. Pedestrians please obey detour signs for safety. Please note: Crews will be working Saturday, September 27 on Highway 7 from Rodick Road to [...]
read more 11275

September 19, 2014

construction work on highway 7 east, sept. 20 – 26

The following lane closures and construction work is scheduled to take place next week on Highway 7 at the intersections indicated below. There are some detours in effect, please look for signage. Pedestrians please obey detour signs for safety. Please note: Crews will be working Saturday, September 20 on Highway 7 from Fairburn to South [...]
read more 11207

September 12, 2014

construction work on highway 7 east, sept. 13 –19

The following lane closures and construction work is scheduled to take place next week on Highway 7 at the intersections indicated below. There are some detours in effect, please look for signage. Pedestrians please obey detour signs for safety. Please note: Crews will be working on Highway 7 on Saturday, September 13 from 7am–2pm. Expect [...]
read more 11002

September 5, 2014

construction work on highway 7 east, sept. 8 – 12

The following lane closures and construction work is scheduled to take place next week on Highway 7 at the intersections indicated below. There are some detours in effect, please look for signage. Pedestrians please obey detour signs for safety. lane closures from saddlecreek drive to leslie street: Eastbound and westbound curb lanes closed intermittently until [...]
read more 10768

August 28, 2014

construction work on highway 7 east, aug. 30 – sept. 5

The following lane closures and construction work is scheduled to take place next week on Highway 7 at the intersections indicated below. There are some detours in effect, please look for signage. Pedestrians please obey detour signs for safety. Please note: Crews will be working Saturday, August 30 on Highway 7 from Warden Avenue to [...]
read more 10586

August 22, 2014

construction work on highway 7 east, aug. 23-29

The following lane closures and construction work is scheduled to take place next week on Highway 7 at the intersections indicated below. There are some detours in effect, please look for signage. Pedestrians please obey detour signs for safety. Please note: Median rapidway paving work continues from Woodbine Avenue to Town Centre Boulevard from 7pm–6am, [...]
read more 10473

August 15, 2014

construction work on highway 7 east, aug. 16-22

The following lane closures and construction work is scheduled to take place next week on Highway 7 at the intersections indicated below. There are some detours in effect, please look for signage. Pedestrians please obey detour signs for safety. Please note: Crews will be working on Saturday, August 16, 7am – 2pm. Expect lane closures [...]
read more 10414
....