Surveying continues on Highway 7 West

What type of work is being done?

Beginning August 24, for approximately a month, land surveyors will be taking measurements along the north side of Highway 7 West between Ansley Grove Road and Pine Valley Drive.

Why is it being done?

To more accurately document existing properties, road conditions and confirm property/project boundaries in preparation for building the vivaNext rapidway.

What impact will this have?

  • There should be little or no impact as surveyors use their portable measuring devices and make every effort to ensure area residents and businesses are not inconvenienced.
  • Some properties may need to be accessed by surveyors, and if your property is fenced and needs to be accessed, you will be personally contacted by our staff or the surveying company, Alex Marton Ltd.

Where and when will the rapidways be built?

Rapidway construction on Highway 7 West will happen in two phases over several years:

Map of vivaNext Highway 7 West rapidway

How can I find out more about this project?

Browse this website for more information about the project and upcoming public open houses, and to sign up for construction updates like this one.

For more information about the vivaNext plan, contact your Community Liaison, Nimisha Raja.

it’s paving season along Highway 7 West in Vaughan

Printer Friendly

It’s an exciting time as the transformation of Highway 7 progresses!

As crews continue work on sidewalks and vivastations, the next segments of paving are beginning at various locations between Edgeley Blvd. and Bowes Rd. Paving will be completed in sections over the next several months and will include closures and detours. Please see below for details. To keep up-to-date, sign up for notices here.

MapMay10

PinkCosta
Scheduled dates: *7pm Wednesday, May 25 to 6am Saturday, May 28
> South side of Highway 7 from Costa to the CN Bridge.
> The Costa Road & Highway 7 intersection will be closed.
> Paid duty police officers will be on site to help direct traffic.

CentreMedianSeg7
Scheduled dates: *7am Thursday, May 26 and 7pm Friday, May 27
> Lane reductions will be enacted to allow for buffer during paving operation.

JanePurple
Scheduled dates: *7pm Friday, May 27 to 6am Monday, May 30
> The middle section of the intersection will be done first, and then south side of the intersection will follow, as crews work around the clock to complete paving activities.
> Detour signs will be in place, and paid duty police officers will be on site to help direct traffic.

* Please note: As with other road construction projects, some work may be rescheduled due to weather or other variables. We are committed to providing advance notice whenever possible.

completed paving segments

EdgeleyJaneMedianOrange
PAVING COMPLETED MAY 18

HillsideGreen
PAVING COMPLETED MAY 18

BaldwinRed
PAVING COMPLETED MAY 8

AquaMedian
PAVING COMPLETED MAY 5

HillsideMedianYellow
PAVING COMPLETED APRIL 29

 

 

 

....