Environmental assessments on Highway 7 West

Where and when is the work being done?

  • Dates: Sunday, January 15 to Tuesday, January 17, 2012.
  • Hours of work: 9am to 3pm.
  • Work location: various locations along Highway 7 West, between Highway 400 and Creditstone Road.

What is being done?

Crews will take measurements and photographs, and visually inspect the roadway and surrounding area.

What impact will this have?

Crew members may be noticeable in the area wearing safety vests and carrying clipboards. Aside from this, this work will not affect residents, businesses, drivers and pedestrians.

Why does this work need to be done?

Environmental assessments need to be completed to prepare for the vivaNext rapidway project. Rapidway construction on Highway 7 West will happen in two phases, starting this year and scheduled to be complete by 2020.

How can I find out more about this project?

Browse this website for more information about the project and upcoming public open houses, and to sign up for construction updates like this one.

For more information about the vivaNext plan, contact your Community Liaison, Nimisha Raja.

it’s paving season along Highway 7 West in Vaughan

Printer Friendly

It’s an exciting time as the transformation of Highway 7 progresses!

As crews continue work on sidewalks and vivastations, the next segments of paving are beginning at various locations between Edgeley Blvd. and Bowes Rd. Paving will be completed in sections over the next several months and will include closures and detours. Please see below for details. To keep up-to-date, sign up for notices here.

MapMay10

PinkCosta
work dates*: Thursday, May 26 to Saturday, May 27
work hours: 7pm–6am, overnight each night
> South side of Highway 7 from Costa to the CN Bridge.
> The Costa Road & Highway 7 intersection will be closed.
> Paid duty police officers will be on site to help direct traffic.

CentreMedianSeg7
work dates*: Thursday, May 26 to Saturday, May 27
work hours: 7pm–6am, overnight each night
> Lane reductions will be enacted to allow for buffer during paving operation.

JanePurple
TO BE RESCHEDULED
.
> The middle section of the intersection will be done first, and then south side of the intersection will follow, as crews work around the clock to complete paving activities.
> Detour signs will be in place, and paid duty police officers will be on site to help direct traffic.

* Please note: As with other road construction projects, some work may be rescheduled due to weather or other variables. We are committed to providing advance notice whenever possible.

completed paving segments

EdgeleyJaneMedianOrange
PAVING COMPLETED MAY 18

HillsideGreen
PAVING COMPLETED MAY 18

BaldwinRed
PAVING COMPLETED MAY 8

AquaMedian
PAVING COMPLETED MAY 5

HillsideMedianYellow
PAVING COMPLETED APRIL 29

 

 

 

....