Lane and road closures along Highway 7 East

During the week of July 18* we will be installing catch basin sewers and continuing watermain work along Highway 7 East.

What are the impacts and details of the watermain work?

Rockwell Road closed at Highway 7. Plaza entrance closure at 360 Highway 7 East (between Rockwell Road and Chalmers Road):
> July 18-22
> Cars can use the alternate entrance off Chalmers Road
> Signs will be in place to inform motorists of the closure

Closure of westbound right turn lane at Highway 7 and Chalmers Road:
> July 20-22

One lane closure may be required on Highway 7, between Valleymede Drive and West Beaver Creek Road:
> July 20-22, 9:30am – 3:30pm

Will any bus stops be affected?
> Westbound curb lane will be closed at Chalmers Road for night work

YRT bus stop at Highway 7 and Chalmers (northeast corner) will be relocated to the northwest side of the intersection:
> July 20-22
> Temporary bus platform will be in place for riders

Lane closures at Highway 7 and Allstate Parkway, starting on south side and moving to the north side. Eastbound curb lane will be closed the first night:
> Week of July 18, over 4-5 nights, 7pm – 7am
> Only one lane closed at a time
> No bus stops will be affected

Thank you for your patience during this time. Work will be completed as quickly as possible to minimize any inconvenience.

Please Note: As with all construction projects, work may need to be rescheduled due to weather. We’ll provide advance notice whenever possible.

For more information about the vivaNext plan and to receive project updates, please visit vivanext.com/highway7_markham, or contact Nimisha Raja, your Community Liaison.

Map showing temporary bus stop relocation.

Map not to scale

meet me in
markham
Journey Image
highway 7 east

Highway 7 East \ Markham and Richmond Hill

project status

under construction

expected completion
2014

85%
completed

view project timeline

Highway 7 Opening for service

Be Ready

Latest Blog

latest updates

construction work, august 30 – september 5

construction work, august 23-29

construction work, august 16-22

all project updates

subscribe to notices

download project newsletter

community liaison

Nimisha Raja

phone 905.886.6767 x71023
cell 416.712.8938
email nimisha.raja@york.ca

Highway 7 East \ Markham and Richmond Hill

Where east meets west.

Markham and Richmond Hill are becoming key destinations within York Region. The Highway 7 East rapidways that travel through both of these municipalities will connect to the Richmond Hill Centre, a new mixed-use urban centre featuring businesses, homes, shops, restaurants, a 10-acre park, a theatre – and you. This is where the planned Yonge North Subway extension will begin (or end). Pick your ride – any ride from the Richmond Hill Centre you’ll find connections to viva, GO, YRT and TTC.

Viva rapid transit service launched on Sunday, August 18 in the centre median, or rapidway, along Highway 7 in Richmond Hill and Markham from Bayview Avenue to Highway 404.  The next phase of rapidway, which totals 3.9 kilometres, along Highway 7 from Highway 404 to Warden Avenue, will open in 2014.  Future plans to extend east to Reesor Road are dependent on additional funding commitments.

photo & video gallery

business profiles

The Route to Shopping

From 7 and Woodbine to Main Street Unionville to Markville Mall, the stretch of Highway 7 has all the shopping you need.

highway 7 east
davis drive
vaughan

....