Skip navigation

Highway 7 nightly lane closures west of Warden

What type of work is being done?

Hydro wires will be installed in Markham at Rodick Road, on the south side of Highway 7. The work will start on Sunday, August 14, from 8:00pm to 6:00am, and will take place over 6 nights. Work will be completed by morning of Saturday, August 20.

What does the work entail?

  • The pavement will be cut across Rodick Road
  • New hydro wires will be installed
  • The existing road will be restored

What impact will there be?

  • Nightly lane closures along Rodick Road will begin for southbound traffic and move to northbound traffic, as work progresses. One lane will be closed at a time
  • Police officers will be on site to manage traffic flow
  • Lanes will be back-filled and paved as work progresses, to keep lanes open during the day
  • The sidewalk will be closed where work is being done
  • Signage will be in place to direct pedestrians
  • There will be continuous noise from the sound of our equipment
  • Work will be completed as quickly as possible to minimize any inconvenience

Will any bus stops be affected?

  • No bus stops will be impacted for this work

Please Note: As with all construction projects, work may need to be rescheduled due to weather. We’ll provide advance notice whenever possible.

For more information about the vivaNext plan and to receive project updates, please visit vivanext.com/highway7_markham, or contact Nimisha Raja, your Community Liaison.

Map of affected area

Map not to scale

meet me in
markham
Journey Image
highway 7 east

Highway 7 East \ Markham and Richmond Hill

project status

under construction

expected completion
2014

70%
completed

view project timeline

Highway 7 Opening for service

Be Ready

Latest Blog

latest updates

construction work, April 21 – 25

construction work, April 14–18

construction work, April 7–11

all project updates

subscribe to notices

download project newsletter

community liaison

Nimisha Raja

phone 905.886.6767 x71023
cell 416.712.8938
email nimisha.raja@york.ca

Highway 7 East \ Markham and Richmond Hill

Where east meets west.

Markham and Richmond Hill are becoming key destinations within York Region. The Highway 7 East rapidways that travel through both of these municipalities will connect to the Richmond Hill Centre, a new mixed-use urban centre featuring businesses, homes, shops, restaurants, a 10-acre park, a theatre – and you. This is where the planned Yonge North Subway extension will begin (or end). Pick your ride – any ride from the Richmond Hill Centre you’ll find connections to viva, GO, YRT and TTC.

Viva rapid transit service launched on Sunday, August 18 in the centre median, or rapidway, along Highway 7 in Richmond Hill and Markham from Bayview Avenue to Highway 404.  The next phase of rapidway, which totals 3.9 kilometres, along Highway 7 from Highway 404 to Warden Avenue, will open in 2014.  Future plans to extend east to Reesor Road are dependent on additional funding commitments.

photo & video gallery

business profiles

The Route to Shopping

From 7 and Woodbine to Main Street Unionville to Markville Mall, the stretch of Highway 7 has all the shopping you need.

highway 7 east
davis drive
vaughan

....