Construction work, Nov. 26–Dec. 3

Doncrest Road to Bayview Avenue

Nightly lane closures in both directions between Doncrest Road and Bayview Avenue for line painting. Please be advised of periodic noise from a waterblasting truck (used for paint removal).

  • November 29, 8pm – 6am

Closure of eastbound and westbound curb lanes to remove poles. Eastbound and westbound curb lanes will not be closed at the same time.

  • November 28-30, 9:30am – 3:30pm

Bayview Avenue

Westbound curb lane closed, west of Bayview Avenue, for removals and excavation work.

  • November 28-30, 9:30am – 3:30pm

Apple Creek Bridge

Eastbound curb lane over Apple Creek Bridge (east of Fairburn Drive) will be closed for watermain work.

  • November 19, 7am – 5pm

Bus Stop Relocations

Please be advised that as part of this construction project, numerous bus stops are being relocated. We will provide details in a future bulletin.

New Project Information Office hours

Please note the Project Information Office hours have changed as follows:

  • Tuesdays and Thursdays, 10am – 4pm
  • Other times by appointment

Please Note: As with all construction projects, work may be rescheduled due to weather. We’ll provide advance notice whenever possible.

For more information about the vivaNext plan and to receive project updates, please see the Highway 7 East rapidway project page, drop by our project information office at Highway 7 and South Park Road, or contact Nimisha Raja, your Community Liaison.

Map of construction work area

Map not to scale

meet me in
markham
Journey Image
highway 7 east

Highway 7 East \ Markham and Richmond Hill

project status

under construction

expected completion
dec. 2014

90%
completed

view project timeline

Highway 7 Opening for service

Be Moved

Latest Blog

latest updates

construction work, September 20 – 26

construction work, september 13 –19

construction work, september 8 – 12

all project updates

subscribe to notices

download project newsletter

community liaison

Nimisha Raja

phone 905.886.6767 x71023
cell 416.712.8938
email nimisha.raja@york.ca

Highway 7 East \ Markham and Richmond Hill

Where east meets west.

Markham and Richmond Hill are becoming key destinations within York Region. The Highway 7 East rapidways that travel through both of these municipalities will connect to the Richmond Hill Centre, a new mixed-use urban centre featuring businesses, homes, shops, restaurants, a 10-acre park, a theatre – and you. This is where the planned Yonge North Subway extension will begin (or end). Pick your ride – any ride from the Richmond Hill Centre you’ll find connections to viva, GO, YRT and TTC.

Viva rapid transit service launched on Sunday, August 18 in the centre median, or rapidway, along Highway 7 in Richmond Hill and Markham from Bayview Avenue to Highway 404.  The next phase of rapidway, which totals 3.9 kilometres, along Highway 7 from Highway 404 to Warden Avenue, will open in December, 2014.  Future plans to extend east to Reesor Road are dependent on additional funding commitments.

photo & video gallery

business profiles

The Route to Shopping

From 7 and Woodbine to Main Street Unionville to Markville Mall, the stretch of Highway 7 has all the shopping you need.

highway 7 east
davis drive
vaughan

....