Demolition program continues on Davis Drive

The final phase of demolitions work will be completed in October and November.

What buildings are being demolished?

When will the work start?

Site preparation began this week and demolition work will begin the week of October 25th.

How long will the demolition and clean up take?

The actual demolition of the buildings will take a few days. The overall
schedule to complete building removal and site clean up for each location
is approximately 35 days. During this time, the property will be fenced and
all activities will be fully monitored and supervised.

Work will be done in accordance with all municipal and regional bylaws
and will meet all health, ecological and regulatory requirements.

be moved

In Newmarket, the future of transit has arrived with the opening of the Viva yellow line on the Davis Drive rapidway. Riders can now enjoy a quick comfortable journey to one of three vivastations at Longford, Main and Southlake, or continue to the Highway 404 park and ride with curbside stops at Huron Heights and Leslie.

With fast, reliable transit and updated utilities in place, Newmarket is prepared for the growth already happening. More travel choices and attractive, tree-lined streets will bring more places to live and work in Newmarket’s downtown. All this goes a long way to improving transit in York Region and all of you are a big part of that. Thank you!

Wondering what this is all about or what a rapidway is? Click here to find out.

....