Warden Station undergoing adjustments

Contractors will begin making adjustments to the prototype vivastation along the rapidway located at Warden Avenue and Enterprise Boulevard in Markham.

How will this affect Viva rapid transit services?

Starting August 19, the Viva rapid transit service will pick up passengers at the temporary vivastations located on the north and south sides of Enterprise Blvd.

When will Warden Station reopen for Viva service?

Warden Station will reopen for Viva service in approximately 2 weeks – as soon as contractors have completed the work.

What changes are being made at Warden Station?

As the prototype rapidway vivastation, various adjustments are being made including some surface materials.

Will ticket machines and PRESTO be available at the temporary vivastations?

  • The ticket machines at the vivastations along Enterprise Blvd. are available for use.
  • For PRESTO transactions, customers may continue to use the equipment in its current location at Warden Station.

Will this work affect traffic or sidewalks in the area?

  • No lane closures or sidewalk detours are expected on Warden Ave. or Enterprise Blvd. as part of this work.
  • Warden Station will be a construction zone, with a fence around the work area for the safety of pedestrians.
  • Viva vehicles will travel in mixed traffic on Warden Ave. and Enterprise Blvd. instead of along the rapidway.
  • The dedicated transit signal will be turned off during this time.

Please Note: As with all construction projects, work may need to be rescheduled due to weather. We’ll provide advance notice whenever possible.

For more information about the vivaNext plan and to receive project updates, please visit vivanext.com/highway7_markham, or contact Nimisha Raja, your Community Liaison.

Warden Station

Map not to scale

follow the progress of the davis drive transformation

contruction banner

Rapidway map

 

Construnction
Complete
54%
as of 2nd quarter


mini photos

more than just a rapidway
rebuilding Davis from the ground up
Davis Drive is approaching its final year of construction and we thank you for bearing with us as we work hard to transform Davis Drive.

construction is challenging
Completely rebuilding Davis is a challenging and complex project that required replacing and relocating outdated utilities and infrastructure under and above ground, before road widening could begin.

what’s to come
Substantial work above ground is underway. Here’s a snapshot of how work is progressing.

 

  • Construction of the vivastation at Parkside/Longford and Davis is underway.
    The steel structure and glass canopy shelter will arrive later this fall.
  • Construction of two more vivastations at Main and Southlake Hospital
    will also begin later this year.
  • The reconstruction of the Keith Bridge will be completed this fall.

viva is coming to davis – dec. 2015
In addition to having a centre-lane bus rapidway, Davis will have wider sidewalks, green open spaces and dedicated left-turn lanes at each intersection that will improve overall traffic flow. All these changes will make Davis an even greater destination to live, work, shop and play.