Demolition program continues at 330 and 338 Davis Drive

As part of the project to improve Davis Drive and build the vivaNext rapidways, twenty one buildings were acquired and will be removed in preparation for construction.

Our environmentally-responsible demolition program will ensure that at least
85% of the materials recovered from these buildings will be reused and/or
recycled, with less than 15% going to landfill.

What buildings are being demolished?

330 and 338 Davis Drive.

Additional demolitions will continue to take place in August and September;
we will continue to provide updates.

When will it start?

Site preparation has begun and demolition will occur the week of August 16, 2010.

How long will the demolition and clean up take?

The actual demolition of the buildings will take a few days. The overall schedule
to complete building removal and site clean up is approximately 30 days. During
this time, the property will be fenced and all activities will be fully monitored
and supervised.

Work will be done in accordance with all municipal and regional bylaws and will
meet all health, ecological and regulatory requirements.

Who is doing this work?

The Cannington Group.

follow the progress of the davis drive transformation

contruction banner

Rapidway map

 

Construnction
Complete
54%
as of 2nd quarter


mini photos

more than just a rapidway
rebuilding Davis from the ground up
Davis Drive is approaching its final year of construction and we thank you for bearing with us as we work hard to transform Davis Drive.

construction is challenging
Completely rebuilding Davis is a challenging and complex project that required replacing and relocating outdated utilities and infrastructure under and above ground, before road widening could begin.

what’s to come
Substantial work above ground is underway. Here’s a snapshot of how work is progressing.

 

  • Construction of the vivastation at Parkside/Longford and Davis is underway.
    The steel structure and glass canopy shelter will arrive later this fall.
  • Construction of two more vivastations at Main and Southlake Hospital
    will also begin later this year.
  • The reconstruction of the Keith Bridge will be completed this fall.

viva is coming to davis – dec. 2015
In addition to having a centre-lane bus rapidway, Davis will have wider sidewalks, green open spaces and dedicated left-turn lanes at each intersection that will improve overall traffic flow. All these changes will make Davis an even greater destination to live, work, shop and play.

Go behind the scenes to see how vivaNext is transforming Davis

....