Construction work, Jan 21–27

Bayview Avenue

Westbound curb lane closed, west of Doncrest Road to Bayview Avenue, to complete drainage work.

  • January 23, 9:30am – 3:30pm

There will be potholing work on the south side of Bayview Avenue but all eastbound lanes will remain open. Please be advised of periodic noise from equipment.

  • January 21 [Saturday], 7am – 4pm

East Beaver Creek Road

Westbound curb lane closed for work to re-instate dedicated right turn lane.

  • January 23-27, 9:30am – 3:30pm

Bus stop relocations

Please be advised that as part of this construction project, numerous bus stops are being relocated. We will provide details in a future bulletin.

Please Note: As with all construction projects, work may be rescheduled due to weather. We’ll provide advance notice whenever possible.

For more information about the vivaNext plan and to receive project updates, please see the Highway 7 East rapidway project page, drop by our project information office at Highway 7 and South Park Road, or contact Nimisha Raja, your Community Liaison.

follow the progress of the davis drive transformation

contruction banner

Rapidway map

 

Construnction
Complete
54%
as of 2nd quarter


mini photos

more than just a rapidway
rebuilding Davis from the ground up
Davis Drive is approaching its final year of construction and we thank you for bearing with us as we work hard to transform Davis Drive.

construction is challenging
Completely rebuilding Davis is a challenging and complex project that required replacing and relocating outdated utilities and infrastructure under and above ground, before road widening could begin.

what’s to come
Substantial work above ground is underway. Here’s a snapshot of how work is progressing.

 

  • Construction of the vivastation at Parkside/Longford and Davis is underway.
    The steel structure and glass canopy shelter will arrive later this fall.
  • Construction of two more vivastations at Main and Southlake Hospital
    will also begin later this year.
  • The reconstruction of the Keith Bridge will be completed this fall.

viva is coming to davis – dec. 2015
In addition to having a centre-lane bus rapidway, Davis will have wider sidewalks, green open spaces and dedicated left-turn lanes at each intersection that will improve overall traffic flow. All these changes will make Davis an even greater destination to live, work, shop and play.

Go behind the scenes to see how vivaNext is transforming Davis

....