Construction work, Feb 26–Mar 2

Bayview Avenue

Eastbound and westbound curb lanes closed to accommodate trucks removing materials.

  • February 27–March 2, 9:30am – 3:30pm

West Beaver Creek Road to Leslie Road

Westbound curb lane closed to pour mudslab.

  • February 27–March 2, 9:30am – 3:30pm

Leslie Street

Westbound left turn lane closed for median work.

  • February 27–March 2, 9:30am – 3:30pm

Woodbine Avenue to Rodick Road

Eastbound and westbound centre lanes closed for median removals and paving.

  • February 28–March 3, 9:30am – 3:30pm

Allstate Parkway to Rodick Road

Curb lanes closed, eastbound and westbound at various locations east of Allstate Parkway, for utility work.

  • February 27–March 16, 9:30am – 3:30pm

South Town Centre Boulevard to Cedarland Drive

Curb lanes closed, northbound and southbound at various locations south of Highway 7, for utility work.

  • February 27–March 16, 9:30am – 3:30pm

Parking impacts on Cedarland Drive

We will be working on Cedarland Drive between South Town Centre Boulevard and Warden Avenue for potholing work. You will need to park on the opposite side of where work is taking place.

  • February 27–March 3 (south side), 7am – 5pm
  • March 5–9 (north side), 7am – 5pm

For more information about the vivaNext plan and to receive project updates, please see the Highway 7 East rapidway project page, drop by our project information office at Highway 7 and South Park Road, or contact Nimisha Raja, your Community Liaison.

map of construction locations

map not to scale

follow the progress of the davis drive transformation

contruction banner

Rapidway map

 

Construnction
Complete
54%
as of 2nd quarter


mini photos

more than just a rapidway
rebuilding Davis from the ground up
Davis Drive is approaching its final year of construction and we thank you for bearing with us as we work hard to transform Davis Drive.

construction is challenging
Completely rebuilding Davis is a challenging and complex project that required replacing and relocating outdated utilities and infrastructure under and above ground, before road widening could begin.

what’s to come
Substantial work above ground is underway. Here’s a snapshot of how work is progressing.

 

  • Construction of the vivastation at Parkside/Longford and Davis is underway.
    The steel structure and glass canopy shelter will arrive later this fall.
  • Construction of two more vivastations at Main and Southlake Hospital
    will also begin later this year.
  • The reconstruction of the Keith Bridge will be completed this fall.

viva is coming to davis – dec. 2015
In addition to having a centre-lane bus rapidway, Davis will have wider sidewalks, green open spaces and dedicated left-turn lanes at each intersection that will improve overall traffic flow. All these changes will make Davis an even greater destination to live, work, shop and play.

Go behind the scenes to see how vivaNext is transforming Davis

....