Retaining Wall Construction – 20 & 54 Davis Drive

Construction of a retaining wall has started at 20 and 54 Davis Drive, the Goodwill plaza just east of Yonge Street.

When will this start?

Crews are on site and have started excavating. Work is scheduled from May 30 to early September, 2011.*

What will this work look like?

Work will include removing existing asphalt and/or curb, excavating earth and building the retaining walls. Once the walls are built, a handrail will be installed and the surrounding area will be restored.

Note: Access to the plaza from Davis Drive will be maintained.

What will the wall be made of?

The wall is being built using stone blocks. The height of the wall at its maximum is approximately 1.1 m (3.6 ft), and walls measuring 0.6 m (2 ft) or more in height will have a handrail installed.

Will sidewalks in the work area be impacted?

The sidewalk will be detoured at times, and in these cases flag personnel will guide pedestrians. If the sidewalk needs to be closed, pedestrians will be directed to the sidewalk on the north side of Davis Drive.

Will there be traffic impacts on Davis Drive?

From time to time there may be temporary lane closures to facilitate the work. Any lane closures will follow permit guidelines and roadways will be clearly signed.

If you have questions about the Davis Drive rapidway project, please contact Andrea Witty, Community Liaison Specialist at andrea.witty@york.ca or 1-877-464-9675, ext. 1022.

*All dates subject to change; advance notice will be provided whenever possible.

Map of construction area where retaining walls will be at 20-54 Davis Drive (Goodwill plaza)

meet me in
Newmarket
Journey Image
davis drive

Davis Drive / Newmarket

project status

under construction

expected completion
Dec. 2015

70%
completed

view project timeline

latest updates

traffic changes on Davis Drive at Patterson Street/Roxborough Road

paving continues on Davis Drive

construction update for Davis Drive

all project updates

subscribe to notices

view project newsletter

Community Liaison

Kristina Bergeron

phone 905.886.6767 x71051
cell 905.505.1347
kristina.bergeron@york.ca

Davis Drive / Newmarket

important changes to traffic patterns and intersections

Charming town where history and vitality mix.

Pedestrian-friendly boulevards; green, open spaces; a vibrant corridor that brings the community together to dine and relax, live, work and shop. Sounds like a dream? Pinch yourself and keep reading.

An exciting new viva rapidway along Davis Drive will change the way we experience our community. Upon completion, the rapidway will immediately make it easier for staff, patients, visitors and volunteers of the Southlake Regional Health Centre to get to the hospital. Over time, Davis Drive will become an attractive urban destination to work, dine, relax, live and shop.

This rapidway will move east along Davis Drive from Yonge Street to just past the hospital. About 2.6 km, to be exact. Then we’ll keep it going another 2.3 km to Highway 404 – this stretch will run the same way viva service currently does, in the curbside lane.

After preparations on properties were done along Davis Drive, construction started in the Davis Drive right-of-way in May 2012. Are we there yet? We’re in the home stretch… the rapidway will open in December 2015.

photo & video gallery

business profiles

(New) Markets

Davis Drive has really come to life over the last few years. There are so many lifestyle options—dining, takeout, the latest fashions, home décor, and health services to name just a few.

highway 7 east
davis drive
vaughan

in the news

....