Octoberr 27, 2017
Utility crews will be performing restoration activities and connecting utilities along Yonge Street next week. Please see below for more information.
utility connections at Yonge and High Tech
Starting Monday, utility crews will be completing underground utility connections on the northeast corner of the Yonge and High Tech Road intersection.
work dates*: Monday, October 30 – Friday, November 3
work hours: 7am-7pm
what you need to know
paving and restoration work at Yonge and Carrville/16th
Starting Tuesday, utility crews will also be completing restoration and paving work on the northwest corner of Yonge Street and Carrville Road.
work dates*: Tuesday, October 31 – Friday, November 3
work hours: 7am-7pm
what you need to know
*Please note: As with all construction projects, some work may be re-scheduled due to weather. We’ll provide advance notice when possible. Watch twitter.com/vivanext for last-minute updates.
We understand that construction can be disruptive and we thank you for your patience. If you have any questions or concerns, please don’t hesitate to contact us.