overnight utility investigations continue on Yonge between High Tech and Beresford

September 05, 2017

Hello,

Crews are scheduled to continue overnight underground utility investigations along the east side of Yonge Street from High Tech Road to Beresford Drive.

work dates*: Tuesday, September 5 and Wednesday, September 6 
work hours: 7pm-7am, overnight

what you need to know

  • Overnight, crews will be locating underground utilities using a hydrovac [truck-mounted vacuum] between High Tech and Beresford. Each hole will be filled before crews move to the next location.
  • To accommodate this work, at times, there will be temporary northbound lane closures on Yonge around work areas.
  • There will be construction-related noise from equipment and trucks.

*Please note: As with all construction projects, some work may be re-scheduled due to weather. We’ll provide advance notice when possible. Watch twitter.com/vivanext for last-minute updates.

We understand that construction can be disruptive and we thank you for your patience. If you have any questions or concerns, please don’t hesitate to contact us.