utility investigations from Highway 407 to 19th Ave/Gamble Rd

May 07, 2015

Crews will continue underground utility investigations along Yonge Street in Richmond Hill in preparation for Yonge Street rapidway construction that begins this year. Please see details below.

Dates of work*: Friday, May 8 – Friday, June 19, 2015
Hours of work*: 7:00am – 7:00pm
Work locations: Various locations along Yonge Street from Highway 407 to just north of 19th Avenue/Gamble Road.

Crews will be locating underground utilities using a hydrovac [truck-mounted vacuum]. Each hole will be filled before crews move to the next location.

What you need to know:

  • There will be temporary alternating north and southbound lane closures on Yonge Street as crews move along the corridor
  • Due to the hydrovac truck vacuum, there will be noise associated with this work
  • Access to driveways will be maintained in work areas
  • Wherever possible, sidewalks and bus stops will remain open. If a sidewalk/bus stop is closed, directional signs will be posted to guide pedestrians

If you have any questions or concerns, please don’t hesitate to contact me.

Yonge Street Rapidway
Leslie Pawlowski | Community Liaison | 905.505.1430 | leslie.pawlowski@york.ca

*Please note: As with other road construction projects, some work may be rescheduled due to weather. We’ll provide advance notice whenever possible.