April 02, 2015
Crews will continue underground utility investigations along Yonge Street in Newmarket next week in preparation for Yonge Street rapidway construction that begins this year. Please see details below.
Dates of work*: Tuesday, April 7, to Friday, April 24, 2015
Hours of work*: 7am-7pm
Work locations: Various locations and intersections along Yonge Street from Savage Road/Sawmill Valley Drive to just south of Davis Drive.
What you need to know:
If you have any questions or concerns, please don’t hesitate to contact me.
Yonge Street Rapidway
Leslie Pawlowski | Community Liaison | 905.505.1430 | leslie.pawlowski@york.ca
*Please note: As with other road construction projects, some work may be rescheduled due to weather. We’ll provide advance notice whenever possible.