April 6, 2018
The transformation is underway along Yonge Street in Richmond Hill. Crews have been busy installing and relocating underground infrastructure, including hydro and telecommunications, and are scheduled to start road widening and storm sewer installation on the east side of Yonge, between the Hwy 407 off-ramp and the Yonge Connector Road, next week. Please see below for more details.
work dates*: Monday, April 9, for approximately two months
work hours*: 7am-7pm, weekdays
description of the road widening process:
general impacts:
*Please note: As with all construction projects, some work may be re-scheduled due to weather. We’ll provide advance notice when possible. Watch twitter.com/vivanext for last-minute updates.
We understand that construction can be disruptive and we thank you for your patience. If you have any questions or concerns, please don’t hesitate to contact me.