Starting tomorrow, crews will be installing a duct bank [a structure which gathers together and encases telecommunication cables] across Gamble Road, at Yonge Street, starting on the northwest corner, working south.
work dates*: Tuesday, February 27 – Thursday, March 1
work hours*: 7am-7pm
what you need to know:
stage 1:
-
Crews will be installing a duct bank across Gamble, starting on the northwest corner, working south.
-
To accommodate this work, westbound traffic will be reduced to one thru-lane, within the work zone, east and west of the intersection.
-
Dedicated right- and left-turn lanes onto Yonge will be maintained for the duration of this work.
-
Crews will backfill and steel plate the work area at the end of each day.
stage 2:
-
Crews will progress south across Gamble.
-
To accommodate this work, eastbound traffic on Gamble will be reduced to a shared left- and thru-lane.
-
Westbound traffic on 19th will also be reduced to one thru-lane. The dedicated left and right onto Yonge, from 19th, will be maintained.
-
Crews will backfill and steel plate the work area at the end of each day.
stage 3:
-
Crews will then install the duct bank on the southwest corner of the intersection.
-
To accommodate this work, eastbound traffic on Gamble will be reduced to one shared thru- and right-turn lane. The dedicated left-turn lane onto Yonge will be maintained.
-
The sidewalk located on the southwest corner of the intersection will be temporarily closed for the duration of this work.
-
After this work area has been backfilled, crews will pave the entire work area.
other details:
-
Paid duty police officers will be onsite for the duration of this work.
-
Access to businesses and properties near the work area will be maintained.
-
Wherever possible, sidewalks will remain open. If a sidewalk is closed, directional signage will be onsite to guide pedestrians to the nearest open sidewalk.
-
Please expect delays, give yourself enough time to get to your destination, and remember to reduce your speed through construction zones.
*Please note: As with all construction projects, some work may be re-scheduled due to weather. We’ll provide advance notice when possible. Watch twitter.com/vivanext for last-minute updates.
We appreciate your patience and apologize for any inconvenience. Should you have any questions, please do not hesitate to contact us.
Sindiswa Moyo | Community Liaison | 289.338.6733 | sindiswa.moyo@york.ca
Leslie Pawlowski | Community Liaison | 905.505.1430 | leslie.pawlowski@york.ca