Crews are progressing with the installation of utilities along Yonge Street in Richmond Hill. Starting Monday, crews will install a duct bank [a structure which gathers together and encases utility cables] across Elgin Mills Road West, starting on the northwest corner, working south.

work dates*: Monday, December 4, for approximately 2 weeks
work hours: 7am-7pm, with staging in place 24/7

stage 1:

  • Crews will be installing a duct bank across Elgin Mills, starting on the northwest corner, working south.
  • To accommodate this work, westbound traffic on Elgin Mills will be reduced to one thru-lane, within the work zone, east and west of the intersection.
  • Dedicated right- and left-turn lanes onto Yonge will be maintained for the duration of this work.
  • The sidewalk located on the northwest corner of the intersection will be temporarily closed for the duration of this work.
  • Crews will backfill and pave the work area before moving to the second stage.

stage 2:

  • Crews will progress south across Elgin Mills.
  • To accommodate this work, eastbound and westbound traffic on Elgin Mills will be reduced to one thru-lane, within the work zone, east and west of the intersection.
  • Dedicated right- and left-turn lanes onto Elgin Mills West will be maintained for the duration of this work.
  • Crews will backfill and pave the work area before moving to the third stage.

stage 3:

  • Crews will move to the southwest corner of the Yonge and Elgin Mills intersection.
  • Eastbound traffic on Elgin Mills West will be reduced to one shared thru- and right-turn lane. A dedicated left-turn lane, onto Yonge, will be maintained for the duration of this work.
  • Follow directional signage for bus stop pick-up on the southwest corner of the intersection.

other details:

  • The west side crosswalk will be closed for the duration of this work. Pedestrians are encouraged to cross Elgin Mills on the east side of the intersection.
  • Traffic control staff and paid duty police officers will be onsite, as required.
  • Access to businesses and properties near the work area will be maintained.
  • Please expect delays and give yourself enough time to get to your destination, and remember to reduce your speed through construction zones.
  • Due to the nature of this work, at times, there will be construction-related noise and dust from equipment and trucks.

*Please note: As with all construction projects, some work may be re-scheduled due to weather. We’ll provide advance notice when possible. Watch twitter.com/vivanext for last-minute updates.

With the weekend upon us, remember to stop by Yonge Street to shop & dine! During construction, your local business owners want to remind you to keep shopping and using services along Yonge. They appreciate the support and look forward to seeing you.

Sindiswa Moyo | Community Liaison | 289.338.6733 | sindiswa.moyo@york.ca
Leslie Pawlowski | Community Liaison | 905.505.1430 | leslie.pawlowski@york.ca