June 19, 2015
Paving is almost complete in the Highway 7 and South Town Centre Boulevard area. Crews will be applying a base layer of paving in the intersection of South Town Centre and Cedarland Drive, followed by a final top layer of paving in the traffic lanes of Town Centre Boulevard just south of Cox Avenue, down South Town Centre to just south of Cedarland. The final paving of the red asphalt in this section of rapidway will take place at a later date this summer.
Paving is highly weather-dependent, so the dates or times may change. Please see the information below about impacts and lane closures.
Location: West side of the intersection at South Town Centre and Cedarland
Dates/Times: Starting as early as Wednesday, June 24, 7pm – 5am*
Description:
Location: Town Centre/South Town Centre, Cedarland and Clegg Road
Dates/Times: overnight from 7pm Thursday, June 25 to 5am Friday, June 26*
Description:
7pm Thursday to 1am Friday [see map, below left], crews will apply a top layer of pavement to the following locations:
Sidewalks and crosswalks will remain open, and Viva buses will continue to travel this section of rapidway during regular operating hours.
1am to 5am on Friday [see map, below right], crews will apply a top layer of pavement to the following locations:
Sidewalks and crosswalks will remain open, and Viva buses will resume service along this section of rapidway during regular operating hours on Friday
We understand that construction can be disruptive and we thank you in advance for your patience. Please contact me if you have any questions or concerns. To learn more about the project, please visit vivanext.com
If you have questions about the rapidway project, please visit vivanext.com, or contact your community liaison team.
Linda Filippi
Manager, Community Liaisons
Tel: 905.886.6767 Ext. 71057
Cell: 905.505.0541
Email: linda.filippi@york.ca
Please note: As with all construction projects, some work may be rescheduled due to weather. We’ll provide advance notice whenever possible.