October 10, 2014
The following paving work is scheduled to take place this week on Highway 7 East at the areas indicated below. Please be advised that this work is weather dependent, and there will be noise and significant traffic delays. Please follow detour signs and give yourself enough time to get to your destination or plan alternate routes.
Crews will be paving east and westbound lanes on Highway 7, between Lunar Court and Town Centre Boulevard, on Wednesday, October 15 and Thursday, October 16. Each day, work will take place from 4am to approximately midnight. Please be advised of the following impacts:
Paving work at the intersections of Montgomery Court and Rodick Road at Highway 7 will be completed on October 17 from approximately 4am to 5pm. The intersections at both locations will remain open with paid duty officers directing traffic. Please be advised of the following impacts:
Please click here for next week’s unrelated paving lane closures.
bus stop impacts:
We understand that construction can be disruptive and we thank you in advance for your patience. Please contact me if you have any questions or concerns.
Please note: As with all construction projects, some work may be rescheduled due to weather. We’ll provide advance notice whenever possible.
Linda Filippi
Manager, Community Liaisons
Tel: 905.886.6767 Ext. 71057
Cell: 905.505.0541
Email: linda.filippi@york.ca