storm sewer work continues on Highway 7

October 20, 2017

Starting next week, crews are continuing storm sewer installations along Highway 7 West at Weston Road and at Pine Valley Drive. To accommodate this work, there will be sidewalk and lane closures. Please see below for further details.

Map: Highway 7 West work area
work dates*: Monday, Oct. 23 to Friday, Nov. 3
work hours*: 7am–5pm
  • To accommodate storm sewer work, the sidewalk on the north side of Highway 7 West between the bus stop on the northeast corner of Weston Road and the ramp coming from southbound Highway 400 will be closed, along with the right turn lanes.
  • Pedestrians will be detoured to the sidewalk on the south side of Highway 7 West. Directional signs will be posted on site.

storm sewer work at Pine Valley Drive:

work dates*: Monday, Oct. 23 to Friday, Nov. 3
work hours*: 7am–5pm
  • To accommodate storm sewer work, the eastbound curb lane will be closed between Pine Valley and Marycroft.
  • Pedestrians will be detoured to the sidewalk on the north side of Highway 7 West. Directional signs will be posted on site.
general impacts:
  • Due to the nature of this work, there will be construction-related noise and dust from equipment and trucks. Directional signs will be posted on site.
  • Please give yourself enough time to get to your destination, and remember to reduce your speed through construction zones.

*Please note: As with other road construction projects, some work may be rescheduled due to weather or other variables. We are committed to providing advance notice whenever possible. Check twitter.com/vivanext for last-minute updates.

If you have any questions or concerns, please don’t hesitate to contact me.

Michelle Goland
Community Liaison Specialist
cell:416.797.5653
email: michelle.goland@york.ca