Saturday work on Highway 7 at Millway

November 11, 2016

Tomorrow, westbound Highway 7 West will be reduced to one lane from west of Jane Street to west of Millway Avenue for paver stone work, constructing the median east of Bowes Road/Baldwin Avenue, and there will be an eastbound Highway 7 traffic shift in the VMC area on Monday. Please see below for details on this work:

westbound lane closure at Millway

work dates*: Saturday, Nov. 12
work hours*: 7:00am to 5:00pm

  • For crews to complete paver stone work, westbound Highway 7 will be reduced to one lane from west of Jane to west of Millway.

left turn lane reduction at Baldwin

work dates*: Saturday, Nov. 12, Monday, Nov. 14 and Tuesday, Nov. 15
work hours*: 7:00am to 5:00pm [closure 24hrs/day]

  • Crews will be working on the median on Highway 7 east of Baldwin on Saturday, Monday and Tuesday, weather permitting.
  • For crews to complete this work, the westbound Highway 7 left turn lane onto Baldwin will be reduced.

eastbound traffic shift in VMC area

work dates*: Monday, Nov. 14
work hours*: 7:00am to 5:00pm

  • Both lanes of eastbound traffic along Highway 7 through the VMC area [Interchange Way to Jane] will be shifted toward the curb.

Please give yourself enough time to get to your destination, and remember to reduce your speed through construction zones.

*Please note: As with other road construction projects, some work may be rescheduled due to weather or other variables. We are committed to providing advance notice whenever possible.

Thank you for your patience as we transform Highway 7. If you have any questions or concerns, please don’t hesitate to contact your Community Liaison.