westbound traffic shift and lane closures on Highway 7 at the CN Bridge

October 13, 2016

Crews will be working at the CN Bridge on Highway 7 West starting Friday during the day, and then overnight Saturday. Please read on for details on this work.

work dates*: Friday, Oct. 14 to Sunday, Oct. 15
work hours*: 9:30am–3:30pm Friday, 7pm–6am Saturday, with lane shift in place 24hrs/day

  • Starting Friday and overnight Saturday, crews will be installing rubber seals and performing a water seal test on Highway 7 West on the CN Bridge.
  • On Friday, westbound lanes will be shifted away from the median and towards the curb, with no lane reductions.
  • On Saturday night, traffic will be reduced to one lane in each direction to accommodate this work, and traffic will shift again as work progresses.
  • Traffic will return to its regular configuration on Sunday morning.
  • Please give yourself enough time to get to your destination, and remember to reduce your speed through construction zones.

*Please note: As with other road construction projects, some work may be rescheduled due to weather or other variables. We are committed to providing advance notice whenever possible.

Thank you for your patience as we transform Highway 7. If you have any questions or concerns, please don’t hesitate to contact your Community Liaison.