September 23, 2016
Tonight, crosswalks will be installed at the Highway 7 W and Edgeley Blvd./Interchange Way intersection, with prep work happening at Highway 7 W and Keele St. In addition, the curb lane will be closed on Highway 7 W from the GO Barrie Bridge to Keele Street. Plus, activation of new traffic signals at Maplecrete Rd. and Highway 7 has been postponed until Wednesday, Sept. 28. Please see below for details on temporary lane reductions and traffic impacts:
work dates*: Friday, Sept. 23 to Saturday, Sept. 24
work hours*: 8pm–6am, overnight
work dates*: Monday, Sept. 26 to Thursday, Sept. 29
work hours*: 8am–8am
*Please note: As with other road construction projects, some work may be rescheduled due to weather or other variables. We are committed to providing advance notice whenever possible.
Thank you for your patience as we transform Highway 7. If you have any questions or concerns, please don’t hesitate to contact your Community Liaison.