curb and median work on Highway 7 West

July 26, 2016

Please read on for details about planned construction activities for the remainder of this week.

curbs at Keele Street, Creditstone Road and Jane Street

Starting today, crews are pouring sections of new curbs at the intersections of Hwy 7 and Keele, Creditstone and Jane.

work dates*: Tuesday, July 26 to Friday, July 29
work hours*: 7am–7pm, 24 hours per day

  • The westbound right-turn lanes are closed at each intersection.
  • The southbound right-turn lane on Keele will be closed at the intersection.
  • Drivers will still be able to turn right from the through lanes at each intersection.
  • The northbound curb lane on Keele, just north of Hwy 7 will be closed.
  • Lane closures will be in place for the duration of this work.
  • Please give yourself enough time to get to your destination, and remember to reduce your speed through construction zones.

median work at Bowes Road

On Thursday, crews will be working on the median at the intersection of Hwy 7 and Bowes Road/Baldwin Avenue.

work dates*: Thursday, July 28 to Friday, July 29
work hours*: 7am–7pm, 24 hours per day

  • The westbound left-turn lane on Hwy 7 will be reduced at the intersection.
  • Please give yourself enough time to get to your destination, and remember to reduce your speed through construction zones.

*Please note: As with other road construction projects, some work may be rescheduled due to weather or other variables. We are committed to providing advance notice whenever possible.

Thank you for your patience as we transform Highway 7 West. If you have any questions or concerns, please don’t hesitate to contact your Community Liaison.