Please read on for details about planned construction activities for the remainder of this week.
Starting today, crews are pouring sections of new curbs at the intersections of Hwy 7 and Keele, Creditstone and Jane.
work dates*: Tuesday, July 26 to Friday, July 29
work hours*: 7am–7pm, 24 hours per day
On Thursday, crews will be working on the median at the intersection of Hwy 7 and Bowes Road/Baldwin Avenue.
work dates*: Thursday, July 28 to Friday, July 29
work hours*: 7am–7pm, 24 hours per day
*Please note: As with other road construction projects, some work may be rescheduled due to weather or other variables. We are committed to providing advance notice whenever possible.