June 17, 2016
Construction is in full swing on the Highway 7 West corridor, as crews work to open the rapidway east of Jane Street later this year. See below for details on upcoming overnight work and lane reductions.
median work
Starting Monday, crews will be installing new medians on several side streets off of Hwy 7, between Edgelely Blvd./Interchange Way and Keele Street.
work dates*: Monday, June 20 to Monday, July 4
work hours: 7am–5pm
overnight line painting
Crews will also be line painting overnight in various locations along the corridor.
work dates*: Monday, June 20 to Tuesday, June 21
work hours: 7pm–6am
Bathurst & Centre construction updates
Rapidway construction in the Bathurst Street and Centre Street corridor is ramping up. To stay up to date on work taking place in the area, subscribe to construction updates at vivanext.com/subscribe.
*Please note: As with other road construction projects, some work may be rescheduled due to weather or other variables. We are committed to providing advance notice whenever possible.
Thank you for your patience as we transform Highway 7. If you have any questions or concerns, please don’t hesitate to contact your Community Liaisons.