As crews continue moving underground telecommunications, work on the second segment will begin on the south side of Highway 7 West, between the CN Bridgeand Keele Street.

Dates: Work begins on November 11, for approximately 16 weeks*
Hours of work: 7am to 7pm
Work locations: Crews will be working on the boulevards and in the curb lanes along the south side of Highway 7, from the CN Bridge to east of Keele Street.

CB_H2_2013_11_07_map

description of work:

Crews will be digging an open trench that will encase telecommunication wires [duct bank] underground and re-building underground maintenance holes, along the south side of Highway 7 West.

what impacts will there be?

  • There will be temporary eastbound curb lane closures along Highway 7 West from the CN Bridge to east of Keele Street. There will also be a temporary southbound curb lane closure at the Keele Street intersection.
  • Wherever possible, sidewalks will remain open. If a sidewalk is closed, directional signage will be on site to guide pedestrians.
  • Access will be maintained to driveways in work areas.
  • Some bus stop relocations will be required for this work. Where bus stops are affected, directional signs will guide pedestrians to the nearest open bus stop.
  • Traffic control staff and paid duty officers will be on site as required.
  • There will be construction-related noise from equipment and trucks.
  • Some weekend work may be required.

Thank you for your patience during this time. If you have any questions about the rapidway project, please call:

Carrie Slattery
Community Liaison
Telephone: 905.886.6767 Ext.1129
Cell: 289.716.0091
Email: carrie.slattery@york.ca

* Please note: As with other road construction projects, some work may be rescheduled due to weather. We’ll provide advance notice whenever possible.