August 22, 2013
An important step in building the vivaNext Highway 7 West rapidway is relocating telecommunications. Crews will begin moving underground telecommunications between Jane Street and the CN Bridge starting on August 26. This work will happen in segments along the corridor. Please see details below about the first segment.
Dates: Starting the week of August 26, for approximately 13 weeks*
Hours of work: 7am to 7pm
Work locations: Crews will be working on the boulevards along the north and south sides of Highway 7, from Jane Street to the CN Bridge.
Crews will be digging an open trench that will encase telecommunication wires [duct bank] underground, along the north and south sides of Highway 7 West.
Thank you for your patience during this time. If you have any questions about the rapidway project, please call Carrie Slattery, Community Liaison at 289.716.0091.
Carrie Slattery
Community Liaison
Telephone: 905.886.6767 Ext.1129
Cell: 289.716.0091
Email: carrie.slattery@york.ca
* Please note: As with other road construction projects, some work may be rescheduled due to weather. We’ll provide advance notice whenever possible.