construction season update for 2017 - Bathurst & Centre

April 10, 2017

Now that the frost is coming out of the ground and spring is in the air, it’s time for a look-ahead for what’s coming up this construction season.

what’s happening on Bathurst & Centre this year

  • Relocating utilities including hydro poles and lines, and telecommunications equipment.
  • Water main and gas main replacement is continuing on Centre Street.
  • Road widening on Bathurst Street begins on the east side of the road and traffic will shift to the west.
  • There will be temporary lane closures around work areas as required.
  • Side street road closures may be required from time to time.
  • On occasion, night and weekend work will be required. Check our website and subscribe to updates at vivanext.com/subscribe.
  • Where possible, bus stops and sidewalks will remain open. Where bus stops and sidewalks are affected, directional signs will guide pedestrians to the nearest available option.
  • Businesses will remain open during construction. Please follow directional signs to access business entrances, sidewalks and bus stops.
  • We will continue to keep everyone informed about project activities and encourage the community to support local businesses through construction.

safety first

  • During construction, crossing at designated crosswalks is more important than ever.
  • When crossing at a designated crosswalk, it’s important to keep safety in mind. Be sure to stop, look, listen - and be aware of your surroundings.
  • When driving, slow down and pay close attention to construction signs and lane markings.

stay informed

sign up for email updates vivanext.com/subscribe



Laura Black
Bathurst & Centre
Community Liaison Specialist
Cell: 905.716.7663
Email: laura.black@york.ca

Michelle Goland
Highway 7 West
Community Liaison Specialist
Cell: 416.797.5653
Email: michelle.goland@york.ca