July 14, 2017
Beginning Sunday overnight, crews will be installing an underground duct bank [a structure which gathers together and encases utility cables] across Centre Street at New Westminster Drive, working over 3 nights. In addition, this weekend, telecommunications work on Bathurst Street will require a curb lane closure. Tree removals north of Highway 7 on Bathurst St. are also scheduled for next week. Please see below for further details.
duct bank installation on Centre:
work dates*: Sunday, July 16 to Wednesday, July 19 [morning]
work hours*: 8pm–6am, overnight
telecommunications work continues on Bathurst:
work dates*: Saturday, July 15 to Sunday, July 16
work hours*: 6am–4pm
tree removals along Bathurst north of Hwy 7:
work dates*: week of Monday, July 17
work hours*: 7am–7pm
general impacts:
*Please note: As with other road construction projects, some work may be rescheduled due to weather or other variables. We are committed to providing advance notice whenever possible. Check twitter.com/vivanext for last-minute updates.
We understand that construction can be disruptive and we thank you in advance for your patience during this time. If you have any questions or concerns, please don’t hesitate to contact me.
Diana Kakamousias |