lane closures on Concord Rd. and Wade Gate

February 22, 2017

Beginning Thursday, there will be lane closures on Concord Road and Wade Gate at Centre Street to accommodate water main drilling. Please see below for further details.

BathurstMap

work dates*: Thursday, Feb. 23 to Friday, Mar. 3 [with closure in effect 24hrs/day]
work hours*: 7am–5pm

what you need to know

  • To accommodate water main drilling work, the northbound through/right-hand turn lane on Wade Gate will be closed, just south of Centre St. Vehicles will use the left-hand turn lane for all movements [left, through, right] at this intersection.
  • Traffic on Concord Rd., just north of Centre, will be shifted westerly. Southbound vehicles will use the right-hand turn lane for all movements [right, through, left] at this intersection.
  • Access to driveways will remain open during this work.
  • A small portion of sidewalk on the south-east corner of Centre and Wade Gate will be closed during this work. In cases where sidewalks are closed around the work areas, directional signs will guide pedestrians to the nearest open sidewalk.
  • Traffic control staff and paid-duty police officers will be on site to direct traffic, as required.
  • Please give yourself enough time to get to your destination, and remember to reduce your speed through construction zones.
  • Due to the nature of this work, there will be construction-related noise from equipment and trucks.

 

*Please note: As with other road construction projects, some work may be rescheduled due to weather or other variables. We are committed to providing advance notice whenever possible.

Thank you for your patience as we transform the Bathurst & Centre area. If you have any questions or concerns, please don’t hesitate to contact me.