hydro pole installation begins on Bathurst Street

February 13, 2017

To accommodate road widening along Bathurst Street, new hydro poles will be installed further back from the road. This week, crews will continue to prepare for hydro pole installation along the west side of Bathurst between Worth Boulevard and Centre Street. Please see below for further details.

BathurstMap

work dates*: Starting Monday, Feb. 13 for several months
work hours*: 9am–4pm

what you need to know

  • For the next week and a half, crews will be excavating and installing the foundations for the new hydro poles along the west side of Bathurst between Worth Blvd. and Centre St.
  • While the majority of work will be taking place within the boulevard area off the road, there may be occasional rolling curb lane closures around the work area.
  • Crews will be moving back and forth along the corridor to complete this work.
  • Bus stops and sidewalks will remain open where possible. If a bus stop or sidewalk is closed, directional signs will guide pedestrians to the nearest open bus stop or sidewalk.
  • Due to the nature of this work, there will be construction-related noise and dust from equipment and trucks.
  • Installation of the new hydro poles will continue over the next few months. We will communicate more details very soon!

stages of hydro pole installation:

  • First, concrete foundations are installed for each new pole location.
  • Then, new poles are delivered and installation continues over a few months.
  • Each pole is about 26 metres long and weighs approximately 8 tonnes.
  • raffic has to be stopped for a short period of time in all directions while each pole is hoisted high in the air over the existing power lines by a large crane. It is then carefully lowered onto concrete foundations. Check out this video [of the vivaNext project on Yonge Street in Newmarket] for a look at how it’s done.
  • Finally, service will be transferred to the new poles. The old poles will be removed and the holes will be backfilled.

*Please note: As with other road construction projects, some work may be rescheduled due to weather or other variables. We are committed to providing advance notice whenever possible.

Thank you for your patience as we transform the Bathurst & Centre area. If you have any questions or concerns, please don’t hesitate to contact me.