removing medians on Centre Street

June 6, 2016

Beginning this week, crews will be removing median strips on Centre St. in preparation for upcoming water main replacement work. Please see below for details:

work dates*: Monday, June 6 to Friday, June 24
work hours: 7am–7pm

  • In preparation for water main replacement work, crews will be removing median strips (the areas that separate opposing lanes of traffic) on Centre Street.
  • Crews will be starting with the median strip that is east of Bathurst St., working their way west towards Dufferin St.
  • This work will require one eastbound and westbound lane closure around each median strip, as crews complete this task in three steps.

1. Medians will be removed, one at a time, moving from east to west.
2. Next, crews will pave each area where median strips were removed.
3. Finally, crews will paint traffic lines.

  • There will be construction-related noise from equipment and trucks.
  • Please give yourself enough time to get to your destination, and remember to reduce your speed through construction zones. In a few weeks’ time, there will be reduced speed limit signs posted. Please keep an eye out for these.

*Please note: As with other road construction projects, some work may be rescheduled due to weather or other variables. We are committed to providing advance notice whenever possible.