June 6, 2016
Beginning this week, crews will be removing median strips on Centre St. in preparation for upcoming water main replacement work. Please see below for details:
work dates*: Monday, June 6 to Friday, June 24
work hours: 7am–7pm
1. Medians will be removed, one at a time, moving from east to west.
2. Next, crews will pave each area where median strips were removed.
3. Finally, crews will paint traffic lines.
*Please note: As with other road construction projects, some work may be rescheduled due to weather or other variables. We are committed to providing advance notice whenever possible.
Laura Black
Community Liaison Specialist
Cell: 905.716.7663
Email: laura.black@york.ca