May 27, 2016
Beginning Monday, crews will be removing median strips on Bathurst St. in preparation for upcoming water main replacement work. Please see below for details, and an update from your Community Liaisons:
work dates*: Monday, May 30 to Friday, June 10
work hours: 9am–4pm
1. Medians will be removed, one at a time, moving from north to south.
2. Next, crews will pave each area where median strips were removed.
3. Finally, crews will paint traffic lines.
*Please note: As with other road construction projects, some work may be rescheduled due to weather or other variables. We are committed to providing advance notice whenever possible.
Laura Black Community Liaison Specialist Cell: 905.716.7663 Email: laura.black@york.ca |
Thank you for your patience as we transform Bathurst & Centre. If you have any questions or concerns, please don’t hesitate to contact me.
Message from Carrie Slattery: It’s been a pleasure working with you all in the community! As I transition to a new role at York Region Rapid Transit Corporation [YRRTC], you are welcome to contact Laura Black moving forward. While many of you already know Laura, she is now the official Community Liaison for the Phase 2 rapidway projects on Highway 7 West and Bathurst & Centre! Over the last few months, Laura has been working diligently, getting to know businesses and residences along the corridors in Vaughan. Whether you’re a property owner, business operator, tenant, or any other interested stakeholder, Laura will be happy to hear from you.