Davis Drive >> overnight paving repairs in sections between Yonge and Roxborough

October 14, 2016

description:

  • Crews will be grinding and re-paving sections along Davis Drive between Yonge Street and Roxborough Road overnight Saturday, October 15.
  • This work is covered by the two-year warranty included in the Davis Drive rapidway project to ensure that quality is maintained for years to come.

locations and noticeable impacts [overnight Saturday, October 15 from midnight–9am*]

  • In sections along Davis, temporary lane closures may be required while crews grind and re-pave areas.
  • On Davis between Bayview and Bolton Avenue, traffic will be reduced to one lane eastbound.

Crews will also complete repairs at:

  • Crews will be grinding and re-paving in the rapidway lanes at Yonge and Davis.
  • Eastbound left-turns at Yonge will not be permitted while crews are working at the intersection. Motorists should proceed to George and make a U-turn.

  • Crews will be grinding and re-paving in the intersection and rapidway lanes at Patterson/Roxborough and Davis.
  • All left-turns at the Davis and Patterson/Roxborough intersection will not be permitted.
  • Drivers will only be able to make right-turns at this intersection.
  • U-turns can be made at the next available intersection.

* Please note: as with other road construction projects, some work may be rescheduled due to weather. We’ll provide advance notice whenever possible.

If you have questions about the rapidway project, please contact your Community Liaison.

Sophia Bittar on behalf of Kristina Bergeron
Community Liaison Specialist
Cell: 905.806.0713
Email: sophia.bittar@york.ca