October 9, 2015
Once the red asphalt is complete on the east end of the corridor, the second phase of black paving will take place from Main Street to east of Huron Heights Drive/Alexander Road. Throughout paving, traffic along Davis Drive will be maintained.
See below for more information on the paving of east and westbound traffic lanes and how to access businesses and side streets during this work.
Crews will begin by paving the south side of Davis from Main to just east of Huron Heights. The next day, crews will pave the north side in the same area.
work dates: Thursday, October 15 – Friday, October 16*
work hours: 7am-7pm*
what you need to know:
Superior Street, Charles Street, and Alexander Road will be closed to traffic at Davis on October 15. Huron Heights Drive, Bolton Avenue, and Bayview Parkway will be closed to traffic at Davis Drive on October 16.
All the best to you and yours this holiday weekend from all of us at vivaNext. Enjoy the fall colours, good food, and the company of family and friends.
As we prepare to open the rapidway, follow us on Twitter to receive ongoing updates.
If you have questions about the rapidway project, please contact your Community Liaison.
Kristina Bergeron
Community Liaison Specialist
Telephone: 905.886.6767 Ext.71051
Cell: 905.505.1347
Email: kristina.bergeron@york.ca
* Please note: As with other road construction projects, some work may be rescheduled due to weather. We’ll provide advance notice whenever possible.