final paving on Davis Drive from Main to Huron Heights

October 9, 2015

Once the red asphalt is complete on the east end of the corridor, the second phase of black paving will take place from Main Street to east of Huron Heights Drive/Alexander Road. Throughout paving, traffic along Davis Drive will be maintained.

See below for more information on the paving of east and westbound traffic lanes and how to access businesses and side streets during this work.

Crews will begin by paving the south side of Davis from Main to just east of Huron Heights. The next day, crews will pave the north side in the same area.

Map: final paving on Davis Drive from Main to Huron Heights, south side

Map: final paving on Davis Drive from Main to Huron Heights, north side

work dates: Thursday, October 15 – Friday, October 16*
work hours: 7am-7pm*

what you need to know:

  • Davis Drive will be reduced to one lane in each direction where paving is taking place.
  • At times, traffic will be shifted to the centre rapidway lanes. Traffic barrels and paid duty police officers will help navigate drivers through the work zone.
  • YRT will continue service on Davis during this activity. Bus stops may be relocated or closed as work progresses. Look for signs and follow directions.
  • Temporary parking will be available on designated side streets. For information on how to access your favourite shops, restaurants and services on Davis, please visit our paving page.
  • Pedestrian access to businesses will be maintained. Follow signs to help guide you to your destination.

road closures: October 15 and 16

Superior Street, Charles Street, and Alexander Road will be closed to traffic at Davis on October 15. Huron Heights Drive, Bolton Avenue, and Bayview Parkway will be closed to traffic at Davis Drive on October 16.

have a safe and happy Thanksgiving weekend

All the best to you and yours this holiday weekend from all of us at vivaNext. Enjoy the fall colours, good food, and the company of family and friends.

As we prepare to open the rapidway, follow us on Twitter to receive ongoing updates.

If you have questions about the rapidway project, please contact your Community Liaison.

Kristina Bergeron

Community Liaison Specialist
Telephone: 905.886.6767 Ext.71051
Cell: 905.505.1347
Email: kristina.bergeron@york.ca

* Please note: As with other road construction projects, some work may be rescheduled due to weather. We’ll provide advance notice whenever possible.