September 28, 2015
Hello,
The transformation of Davis Drive continues as crews switch over to the permanent traffic lights at the intersections of Main Street and Tannery Mall on Davis. Once the new traffic lights are activated, audible pedestrian crossing signals will be available.
work dates: Wednesday, September 30*
work hours: 8am-4pm*
To help ease the flow of traffic along Davis Drive, left-turn traffic sensors will be installed at intersections along the corridor. Overnight this week and next week, crews will be installing sensors between Main Street and Roxborough Road. The sensors will be used to prioritize the advanced green arrow for motorists to make left or U-turns through the intersections.
work dates: Tuesday, September 29 – Friday, October 9*
work hours: overnights from 7pm – 7am*
As we prepare to open the rapidway, follow us on Twitter to receive ongoing updates.
If you have questions about the rapidway project, please contact your Community Liaison.
Kristina Bergeron
Community Liaison Specialist
Telephone: 905.886.6767 Ext.71051
Cell: 905.505.1347
Email: kristina.bergeron@york.ca
* Please note: As with other road construction projects, some work may be rescheduled due to weather. We’ll provide advance notice whenever possible.