update: davis night work rescheduled

October 15, 2014

The night work scheduled to take place this week along and around Davis Drive has been rescheduled due to the changing weather forecast. Please see below for the revised dates and work hours.

paving

The paving that was scheduled to take place overnight starting tonight [October 15-17] has been rescheduled to take place during the day:

Revised dates and times: Friday, October 17 and Saturday, October 18, 7am-7pm*

Paving locations will be the same as previously communicated

    • Portions of Vincent Street and Main Street just north of Davis
    • Along the north side of Davis from east of Bayview Parkway to just west of Patterson Street
    • Portions of Bayview Parkway, Bolton Avenue and Lundy’s Lane just north of Davis

telecommunications installation

Crews have rescheduled the underground telecommunications work to begin overnight next week [7:00pm – 7:00am] in two locations along Davis. Please see revised dates, locations and impacts below.

Locations:

    • Roxborough/Patterson and Davis – Monday, October 20 to Friday, October 31*
    • Main and Davis – Monday, October 20 to Friday, October 24*

Traffic lanes will be reduced around both areas. In the morning, the areas will be plated and re-opened. Police officers will be onsite to direct and manage traffic flow. Please follow directional signs to guide you to the nearest open bus stop or sidewalk.

If you have any questions or concerns, please don’t hesitate to contact me.

Michelle Dudzik
Community Liaison Specialist
Telephone: 905.886.6767 Ext. 71096
Cell: 905.716.7663
Email: michelle.dudzik@york.ca

* Please note: As with other road construction projects, some work may be rescheduled due to weather. We’ll provide advance notice whenever possible.