construction at 17555 Yonge Street

October 8, 2013

Starting in October, crews will begin construction activities in the Shoppers Drug Mart/LCBO/Blinds To Go plaza.

Work date: Starting in October*
Work time: 7am–7pm

stages of work:

  1. Connect the plaza to the newly built temporary parking lot next door to the east [i.e. the old car wash and Cango Gas Station]
  2. Build a driveway to the new temporary parking lot from George Street
  3. Build a retaining wall, backfill, pave and restore the area

access to the Shoppers Drug Mart/LCBO/Blinds To Go plaza [see map]:

  • As crews work in the plaza’s parking lot, pedestrian and vehicle access to the plaza will be maintained from Davis Drive and Yonge Street
  • Once the temporary parking lot is complete, patrons will also be able to access the plaza through George Street
  • Parking will not be available in work areas 

map

bus stop and sidewalk closures:

  • One sidewalk will remain open on Davis Drive. Please follow directional signs
  • Should any bus stops be temporarily relocated, directional signs will guide pedestrians to the new bus stop location

If you have questions about the rapidway project please contact:

Michelle Dudzik 
Community Liaison Specialist
Telephone: 905.886.6767 Ext. 1096
Cell: 905.716.7663
Email: michelle.dudzik@york.ca

Please note: As with other road construction projects, some work may be rescheduled due to weather. We’ll provide advance notice whenever possible.