June 27, 2013
Earlier this year, construction work to widen the north side of the Keith Bridge was paused due to the fish spawning season [April 1 - July 1]. As fish spawning season will be over July 1, crews will resume work on the north side of the bridge starting the week of July 2.
Crews will be using a vibrating hammer and crane to install a cofferdam [which will divert water around the base of the new segment of bridge]. This will allow crews to begin construction of the foundation for the new north side of the bridge.
Work Dates: The week of July 2 for approximately 3 months*
Work hours: 6am-7pm
Note: For the next three months, crews will be performing daily vibration work, Monday to Friday from 8am-6pm. At times, weekend work may be required.
If you have questions about the rapidway project, please visit vivanext.com, or contact:
Michelle Dudzik
Community Liaison Specialist
Telephone: 905.886.6767 Ext. 1096
Cell: 905.716.7663
Email: michelle.dudzik@york.ca
Please note: As with other road construction projects, some work may be rescheduled due to weather. We’ll provide advance notice whenever possible.