Retaining wall construction at 291 Davis Drive

April 02, 2013

Beginning the week of April 1, crews will begin constructing a retaining wall in front of the pharmacy and medical building at 291 Davis Drive.

Dates of work: Beginning the week of April 1 until July*

Work hours: 7am-7pm

Description of work:
  • Excavate the work area
  • Install catch basin
  • Build the retaining wall
  • Build stairs to the east
  • Restore the area
Plaza entrance and parking lot changes during construction:
    • Access to 291 Davis Drive, 8 and 10 Hill Street will remain open. Signs will direct pedestrian and vehicle traffic.
    • The plaza entrance off Hill Street will remain open.
    • Parking will not be available in the work area in front of the building.
    • Plaza parking will continue to be available along the side and back of the building.
    • All entrances to the building will remain open.

 

Bus stop, sidewalk and lane closures:
  • To accommodate utility relocation, Davis Drive traffic will be reduced to one lane in each direction for the duration of the rapidway project.
  • When sidewalk and bus stop closures are required, please follow on site signage.
  • Where sidewalks are affected, onsite signage will direct pedestrians.

If you have questions about the rapidway project, please visit vivanext.com, or contact:

Michelle Dudzik
Community Liaison Specialist
Telephone: 905.886.6767 Ext. 1096
Cell: 905.716.7663
Email: michelle.dudzik@york.ca

Please note: As with other road construction projects, some work may be rescheduled due to weather. We’ll provide advance notice whenever possible.