Multiple lane closures west of Patterson Street

August 31, 2012

As water main work continues and preparations are made for the Eastern Creek culvert construction, Davis Drive will be reduced to two lanes between Bolton Avenue and Patterson Street.

Dates: Starting the week of Tuesday, September 4 for approximately three months*

What’s happening

Traffic lanes on Davis Drive from Bolton Avenue to just west of Patterson Street will be reduced to one lane in each direction, with the centre median lane available for emergency vehicle traffic.

location 

Impacts during construction

  • The sidewalk on the north side of Davis Drive between Bolton Avenue and Patterson Street will be closed. When crossing to the south sidewalk, please use the signalized intersection.
  • At times, the bus stop at Patterson Street and Davis Drive may be temporarily closed for retaining wall construction at 693 Davis. When the stop is closed, westbound transit users will need to board the bus at Lundy’s Lane or Huron Heights Drive.
  • All businesses will remain open during this work. 

Please remember to reduce your speed through construction zones and be mindful of traffic shifts and signs that will help guide you along your way. And if you’re walking, please stay aware of your surroundings by avoiding distractions like phones, ipods and mp3 players.

If you have questions about the rapidway project, please visit vivanext.com, or contact:

Michelle Dudzik
Community Liaison Specialist
Telephone: 905.886.6767 Ext. 1096
Cell: 905.716.7663
Email: michelle.dudzik@york.ca

*Please note: As with other road construction projects, some work will have traffic flow and noise impacts or may be rescheduled due to weather conditions and other variables. We are committed to providing advance notice whenever possible.