August 31, 2012
As water main work continues and preparations are made for the Eastern Creek culvert construction, Davis Drive will be reduced to two lanes between Bolton Avenue and Patterson Street.
Dates: Starting the week of Tuesday, September 4 for approximately three months*
What’s happening
Traffic lanes on Davis Drive from Bolton Avenue to just west of Patterson Street will be reduced to one lane in each direction, with the centre median lane available for emergency vehicle traffic.
Impacts during construction
Please remember to reduce your speed through construction zones and be mindful of traffic shifts and signs that will help guide you along your way. And if you’re walking, please stay aware of your surroundings by avoiding distractions like phones, ipods and mp3 players.
If you have questions about the rapidway project, please visit vivanext.com, or contact:
Michelle Dudzik
Community Liaison Specialist
Telephone: 905.886.6767 Ext. 1096
Cell: 905.716.7663
Email: michelle.dudzik@york.ca
*Please note: As with other road construction projects, some work will have traffic flow and noise impacts or may be rescheduled due to weather conditions and other variables. We are committed to providing advance notice whenever possible.