March 18, 2011
Rapidway construction is well underway. We will now build six retaining walls to allow for utility relocations and the main road construction phase which is scheduled to start in late 2011.
Crews will begin mobilizing on the work sites the week of March 21, 2011.
The walls being constructed at 20, 54 and 350 Davis Drive are approximately 1 metre in height (maximum). Work will include:
Once the wall is built, the area will be restored and a handrail will be installed on the top of the retaining wall.
Yes, access to each location will be maintained. All necessary signage to manage pedestrian and vehicle traffic will be in place.
For the most part, the sidewalks will be kept open for pedestrians. However, an occasional short-term pedestrian detour may be required. When required, detour signs will direct pedestrians to the north side of Davis Drive.
From time to time there may be temporary lane closures. Any lane closures will follow permit guidelines and roadways will be clearly signedand 350 Davis Drive to allow for the tree removals. In all work areas, the sidewalks will be open and a flag person will be on site to direct pedestrians.
If you have questions about Davis Drive rapidway project, please contact Andrea Witty, Community Liaison Specialist at andrea.witty@york.ca or 1-877-464-9675, ext. 1022.