Demolition program continues

September 29, 2010

What buildings are being demolished?

180 Davis Drive and 19 & 23 Parkside Drive

Additional demolitions of buildings acquired for rapidway construction will
continue through October and November. We will provide updates as they
become available.

When will it start?

Site preparation is underway and demolitions will take place the week of
October 4, 2010.

How long will the demolition and clean up take?

The actual demolition of each building will take a few days. The overall schedule to
complete site clean up is approximately 30 days. During this time, the property will
be fenced and all activities will be fully monitored and supervised.

Work will be done in accordance with all municipal and regional bylaws and will
meet all health, ecological and regulatory requirements.

Who is doing this work?

Maram Building Corporation.