August 10, 2010
As part of the project to improve Davis Drive and build the vivaNext rapidways, twenty one buildings were acquired and will be removed in preparation for construction.
Our environmentally-responsible demolition program will ensure that at least
85% of the materials recovered from these buildings will be reused and/or
recycled, with less than 15% going to landfill.
330 and 338 Davis Drive.
Additional demolitions will continue to take place in August and September;
we will continue to provide updates.
Site preparation has begun and demolition will occur the week of August 16, 2010.
The actual demolition of the buildings will take a few days. The overall schedule
to complete building removal and site clean up is approximately 30 days. During
this time, the property will be fenced and all activities will be fully monitored
and supervised.
Work will be done in accordance with all municipal and regional bylaws and will
meet all health, ecological and regulatory requirements.
The Cannington Group.